The following is calculated for the project.Earned value=us$200,000;Planned value=us$300,000;Actual cost=us$210,000.What is the status of the project?
A、Behind schedule and over budget
B、Ahead of schedule and over budget
C、Behind schedule and under budget
D、On schedule and over budget