The duration of a project is five months, The total cost initially allocated was US$30,000. The project is in the third month, The total expenditure in the project for the first two months is us$12,5000. The project is ahead of schedule and on budget for work completed.What is the cost variance of the project?
A、Greater than zero
B、Less than zero
C、Zero
D、One