The project manager identifies candidates for the project team based on needed competencies to deliver the agreed scope. What should the project manager do next?
A、Negotiate with functional managers to allocate the resources to the project
B、Negotiate with the identified resources to join the project
C、Escalate the resource needs to the project sponsor immediately
D、Update the risk management log with the need for competencies