软题库 移动APP 扫码下载APP 随时随地移动学习 培训课程
当前位置:信管网 >> 在线考试中心 >> 信息系统项目管理师题库 >> 试题查看
试卷名称 2017年信息系统项目管理师最新英语模拟题(1)
考试中心《2017年信息系统项目管理师最新英语模拟题(1)》在线考试
试卷年份2017年下半年
试题题型【单选题】
试题内容

Weather conditions are identified as critical risks for an offshore wind park development project. To mitigate risks associated with bad weather conditions, the project manager creates a contingency plan to and more time to the planned schedule. At the time of execution a hurricane comes close to the wind park area so that all activities need to be stopped immediately.What should the project manager next?
A、Update the risk register and create a change request.
B、Get additional approval from the steering committee.
C、Change the schedule of the team members accordingly
D、Avoid any chances to keen the project management plan as if was approved.


相关试题

推荐文章
合作网站内容