A project manager works for a company that does not use formal project management processes as a result, the company has a history of modifying project requirements throughout the life of the project, often resulting in delays in project completions. What should the project manager update in the current project to control further modifications?
A、project scope
B、Change management plan
C、Stakeholder analysis
D、Lessons learned