A contracted firm is not meeting quality standards and the deliverables are frequently late. The project manager discovers there are no existing contract terms that could ensure a better. What should have been done by the project manager to prevent the seller’s low performance?
A、Have the project manager’s team do an impact analysis
B、Conduct procurement performance reviews
C、Conduct a risk reassessment
D、Be involved during the contract elaboration