试题内容

In an eight-month project, the customer requests a change to a complex business requirement. Development is 72% complete. The customer suggests the project schedule be extended by an additional month. What should the project manager do next?
A、Reject the change since most of the development is complete.
B、Ask for additional funds.
C、Analyze the variance.
D、Accept the change since the customer has increased the schedule.