试题题型【单选题】
试题内容

During a meeting, a team member expresses concerns about the performance confidence of the newly developed component. During the stress testing of this components, the project manager notices that the components below the defined performance parameters. What should the project manager do next?
A、Request a corrective action to resolve this issue.
B、Utilize a checklist to limit the probability of failure.
C、Facilitate additional tests to continue examining the component.
D、Use a different tool to test the component thus conforming.