As competition intensifies, a company had to adjust its measures the overall project. The project manager must motivate the project team to achieve a higher level of performance. What should the project manager do next
A、Review the enterprise environmental factor which affects team performance.
B、Consider, recruitment and change the team members to organize a project team.
C、Implementation of incentive systems to improve productivity.
D、Regularly for individual members to implement performance assessment.