The project manager is developing a project plan. On short notice, the project sponsor asks the project manager to create an initial rough estimate of project upcoming fiscal budget. The project manager uses which of the following for estimating the project cost ?
A、Bottom-up estimating
B、Three-point estimating
C、Analogous estimating
D、Parametric modeling