Towards the end of a large infrastructure project the tension rises, and in the conferences, it occurs more frequently. This affects the productivity of the team. The focus of their attention is not to complete the scope of project. To restore order the project manager fired two members. What kind of conflict resolution strategy does the project manager use ?
A、Smoothing
B、 Compromising
C、 Forcing
D、 Collaborating