An international company is looking to expand its organization. Part of the expansion plan includes establishing a series of branch offices in selected geographically place. The project charter has been drafted by the sponsor, who is now seeking the project manager’s help, and finally determine the content of the project.
Below is an exception of the current version of the charter.
Project charter except :
Overall Purpose: Expand the company’s presence in growing markets and offer more local access to private customers.
Objectives:
1. Establish a number of branch offices.
2. Increase the number of private customers.
3. Offer a range of services.
4. High level risks.
5. Limited knowledge of local conditions, rules and regulations.
6. A rapidly developing unstable market.
7. Large number of competitors looking at the same opportunities.
What should be further improved in the project charter to increase the changes of a successful ?
A、Improve the project’s purpose to clarify the overall goal.
B、Improve the risks by developing a set of clear risk response.
C、Improve the objectives and add a definitive measure to each of them.
D、Leave the charter and start converting this into a project management plan.