A company obtained a project in a new region. The project manager identified the risk of the project and the sort. Which of the following actions should the project manager take next?
A、 Plan Risk Responses process.
B、 Develop appropriate measures, and improve the positive risk or opportunity.
C、 Improve opportunities and reduce threats.
D、 Update risk information.