根据批准的商业论证,项目必须在12个月内完成,以最大限度地提高经济效益,在审查商业论证之后,项目经理识

According to the approved business case, a project must be completed within 12 months to maximize financial benefits. After reviewing the business case, the project manager identifies a few constraints that will make it impossible to complete the project within this time frame. What should the project manager do?

根据批准的商业论证,项目必须在12个月内完成,以最大限度地提高经济效益,在审查商业论证之后,项目经理识别到一些制约因素,这些制约因素将导致无法在此时间范围内完成项目,项目经理应该怎么做?

A.Include the 12-month project duration in the project charter在项目章程中包括12个月的项目持续时间

B.Update the project charter with revised completion date after consideration of the impact of these constraints在考虑到这些制约因素的影响后,在项目章程中更新修订后的完成日期

C.Inform management that the project timeline is not achievable通知管理层无法实现项目时间表

D.Meet with management to discuss the matter and finalize an action plan与管理层开会讨论此事并最终确定行动计划

信管网参考答案:D

信管网解析:

D是参考答案。在启动阶段,项目经理需要与管理层沟通,寻求指导,确定合适的行动方案。A,B,C选项可以理解为实施D选项后可能采取的行动。

信管网订阅号

信管网视频号

信管网抖音号

温馨提示:因考试政策、内容不断变化与调整,信管网网站提供的以上信息仅供参考,如有异议,请以权威部门公布的内容为准!

信管网致力于为广大信管从业人员、爱好者、大学生提供专业、高质量的课程和服务,解决其考试证书、技能提升和就业的需求。

信管网软考课程由信管网依托10年专业软考教研倾力打造,教材和资料参编作者和资深讲师坐镇,通过深研历年考试出题规律与考试大纲,深挖核心知识与高频考点,为学员考试保驾护航。面授、直播&录播,多种班型灵活学习,满足不同学员考证需求,降低课程学习难度,使学习效果事半功倍。

相关内容

发表评论  查看完整评论  

报考条件查询

推荐文章

精选

课程

提问

评论

收藏