信息系统项目管理师历年真题英语题翻译与答案[7]
来源:信管网 2016年04月22日 【所有评论 分享到微信

2009年下半年
● The (71) process ascertains which risks have the potential of affecting the project and documenting the risks' characteristics.
(71)A.Risk Identification
B.Quantitative Risk Analysis
C.Qualitative Risk Analysis
D.Risk Monitoring and Control
信管网试题解析:
项目风险管理主要包括编制风险管理计划、风险识别、定性风险分析、定量风险分析、编制风险应对计划和风险监控。
其中,风险识别过程是确定哪些风险可能会对项目产生影响,并将这些风险的特征形成文档。选项A是风险识别,选项B是定量风险分析,选项C是定性风险分析,选项D是风险监控。
信管网参考答案:
(71)A

● The strategies for handling risk comprise of two main types:negative risks, and positive risks. The goal of the plan is to minimize threats and maximize opportunities.When dealing with negative risks,there are three main response strategies (72),Transfer ,Mitigate .
(72)A.Challenge
B.Exploit
C.Avoid
D.Enhance
信管网试题解析:
风险应对策略包括两种类型:负面风险的应对策略和正向风险的应对策略。风险应对计划的目标是最小化威胁,并且最大化机会。处理负面风险有三种典型的策略:回避、转移和减轻。
选项A是挑战,选项B是开发,选项C是回避,选项D是提高。
信管网参考答案:
(72)C

● (73)is a property of object-oriented software by which an abstract operation may be performed in different ways in different classes.
(73)A.Method
B.Polymorphism
C.Inheritance
D.Encapsulation
信管网试题解析:
多态是面向对象的特征之一,它提供了一个抽象操作,在不同的类中能够执行不同的方法。
选项A是方法,选项B是多态,选项C是继承,选项D是封装。
信管网参考答案:
(73)B

● The Unified Modeling Language is a standard graphical language for modeling object-oriented software.(74)can show the behavior of systems in terms of how objects interact with each other.
(74)A.Class diagram
B.Component diagram
C.Sequence diagram
D.Use case diagram
信管网试题解析:
统一建模语言是为面向对象软件建模的一种标准图形语言。顺序图可以根据对象间如何交互来展示系统的行为。
选项A是类图,选项B是组件图,选项C是顺序图,选项D是用例图。
信管网参考答案:
(74)C

● The creation of a work breakdown structure(WBS)is the process of(75)the major project deliverables.
(75)A.subdividing
B.assessing
C.planning
D.integrating
信管网试题解析:
创建工作分解结构是分解项目可交付物的过程。
选项A是分解,选项B是估算,选项C是计划,选项D是整合。
信管网参考答案:
(75)A


2009年上半年
第七十一—七十五题
Many of the activities performed during the preliminary investigation are still being conducted in(71), but in much greater depth than before. During this phase, the analyst must become fully aware of the(72) and must develop enough knowledge about the(73) and the existing systems to enable an effective solution to be proposed and implemented. Besides the(74) for process and data of current system, the deliverable from this phase also includes the(75) for the proposed system.
(71)A. analysis phase B. design phase
C. implementation phase D. maintenance phase
(72)A. main symptom B. root problem
C. final blueprint D. data specification
(73)A. hardware environment B. testing environment
C. software environment D. business environment
(74)A. logical models B. physical models
C. design models D. implementation models
(75)A. hardware and software specification B. system performance specification
C. formal requirements definition D. general problem statement
信管网解析:
初步调研阶段的许多活动在分析阶段仍然要做,但是会比以前更深入地做。在分析阶段,分析师一定要完全清楚最终蓝图并且开发出充分的关于业务环境知识和目前系统的知识以使一个有效的解决方案被提交和实施。除了当前系统的过程和数据的逻辑模型,这一阶段的产出物还包括建议系统的正式需求定义。
信管网参考答案:71A, 72B, 73D, 74A, 75C 
[1]   [2]   [3]   [4]   [5]   [6]   [7]   [8]   [9]   [10]   
扫码关注公众号

温馨提示:因考试政策、内容不断变化与调整,信管网网站提供的以上信息仅供参考,如有异议,请以权威部门公布的内容为准!

信管网致力于为广大信管从业人员、爱好者、大学生提供专业、高质量的课程和服务,解决其考试证书、技能提升和就业的需求。

信管网软考课程由信管网依托10年专业软考教研倾力打造,官方教材参编作者和资深讲师坐镇,通过深研历年考试出题规律与考试大纲,深挖核心知识与高频考点,为学员考试保驾护航。面授、直播&录播,多种班型灵活学习,满足不同学员考证需求,降低课程学习难度,使学习效果事半功倍。

相关内容

发表评论  查看完整评论  

推荐文章