Many of the activities performed during the preliminary investigation are still being conducted in (71), but in much greater depth than before. During this phase, the analyst must become fully aware of the(72) and must develop enough knowledge about the(73) and the existing systems to enable an effective solution to be proposed and implemented. Besides the (74) for process and data of current system, the deliverable from this phase also includes the(75)for the proposed system.
(71)A. analysis phase B. design phase
C. implementation phase D. maintenance phase
(72)A. main symptom B. root problem
C. final blueprint D. data specification
(73)A. hardware environment B. testing environment
C. software environment D. business environment
(74)A. logical models B. physical models
C. design models D. implementation models
(75)A. hardware and software specification B. system performance specification
C. formal requirements definition D. general problem statement

2009年下半年

The (71) process ascertains which risks have the potential of affecting the project
and ics. documenting the risks' characteristics。
(71)A. Risk Identification B. Quantitative Risk Analysis
C. Qualitative Risk Analysis D. Risk Monitoring and Control

● The strategies for handling risk comprise of two main types: negative risks, and positive risks. The goal of the plan is to minimize threats and maximize opportunities. When dealing with negative risks, there are three main response strategies – (72), Transfer, Mite gate.
(72)A. Challeng B. Exploit
C. Avoid D. Enhance igate.
● (73) is a property of object-oriented software by which an abstract operation may be performed in different ways in different classes.
(73) A. Method B. Polymorphism
C. Inheritance D. Encapsulation

● The Unified Modeling Language is a standard graphical language for modeling object-oriented software. (74)can show the behavior of systems in terms of how objects interact with each other.
(74)A. Class diagram B. Component diagram
C. Sequence diagram D. Use case diagram

● The creation of a work breakdown structure (WBS) is the process of (75)the major
Project deliverables.
(75)A. subdividing B. assessing
C. planning D. integrating 

2009年上半年:(71) A (72) B (73) D (74)A (75)C
2009年下半年:(71) A (72) C (73) B (74)C (75)A 

 

[1]   [2]   [3]   [4]   [5]   

信管网订阅号

信管网视频号

信管网抖音号

温馨提示:因考试政策、内容不断变化与调整,信管网网站提供的以上信息仅供参考,如有异议,请以权威部门公布的内容为准!

信管网致力于为广大信管从业人员、爱好者、大学生提供专业、高质量的课程和服务,解决其考试证书、技能提升和就业的需求。

信管网软考课程由信管网依托10年专业软考教研倾力打造,教材和资料参编作者和资深讲师坐镇,通过深研历年考试出题规律与考试大纲,深挖核心知识与高频考点,为学员考试保驾护航。面授、直播&录播,多种班型灵活学习,满足不同学员考证需求,降低课程学习难度,使学习效果事半功倍。

相关内容

发表评论  查看完整评论  

推荐文章

精选

课程

提问

评论

收藏