试题1
为了确定项目成本,项目经理利用一个过往类似项目的实际成本(AC),项目经理使用的是哪—种估算技术?查看答案
试题参考答案:B
试题2
如何定义最小可售单元查看答案
试题参考答案:C
试题3
假设有一项目,其获利100,000美元的概率为60%,损失100.000美元的概率为40%,那么该项目的预期货币价值为∶查看答案
试题参考答案:C
试题解析与讨论:www.cnitpm.com/st/475974815.html
试题4
During project execution, the customer indicates that there will be limited access to the test facility due to several concurrent projects. This change may lead to schedule delays. To minimize the negative impact, what should the project manager do next?查看答案
试题参考答案:B
试题解析与讨论:www.cnitpm.com/st/491684696.html
试题5
如果团队成员表示他们感到过度劳累和压力,敏捷管理专业人士应该怎么做?查看答案
试题参考答案:A
试题解析与讨论:www.cnitpm.com/st/528623005.html
试题6
在项目执行期间,项目经理收到一个新需求的请求。若要确定该请求是否将变更范围。项目经理应查阅哪—份文件?查看答案
试题参考答案:D
试题7
Which of the following are GENERALLY illustrated BETTER by bar charts than network diagrams?和网络图相比,甘特图能更好的表明∶查看答案
试题参考答案:D
试题8
如果团队质疑每日站会的意义。敏捷管理专业人士应该怎么做?查看答案
试题参考答案:A
试题9
A project manager was been assigned to a large enterprise located in another country. The project manager has planned the project properly and conducted all the phases of the project with success. Currently, the project manager is collecting the lessons learned during the project.In what stage is the project manager?查看答案
试题参考答案:D
试题10
A particular stakeholder has a reputation for making many changes on projects. What is the BEST approach a project manager can take at the beginning of the project to manage this situation?()查看答案
试题参考答案:B
试题解析与讨论:www.cnitpm.com/st/494996916.html
信管网订阅号
信管网视频号
信管网抖音号
温馨提示:因考试政策、内容不断变化与调整,信管网网站提供的以上信息仅供参考,如有异议,请以权威部门公布的内容为准!
信管网致力于为广大信管从业人员、爱好者、大学生提供专业、高质量的课程和服务,解决其考试证书、技能提升和就业的需求。
信管网软考课程由信管网依托10年专业软考教研倾力打造,教材和资料参编作者和资深讲师坐镇,通过深研历年考试出题规律与考试大纲,深挖核心知识与高频考点,为学员考试保驾护航。面授、直播&录播,多种班型灵活学习,满足不同学员考证需求,降低课程学习难度,使学习效果事半功倍。
发表评论 查看完整评论 | |