信息系统项目管理师考试英语练习题(九)

信息系统项目管理师考试英语练习题(九)

1、The project maintains a current and approved set of requirements over the life of the project by doing  the following:  

( ) all changes to the requirements  Maintaining  the relationships among  the requirements, the project plans,  and the work products  

A. Monitoring        

B. Managing      

C. Gathering          

D. Reducing    

信管网解析:

项目通过执行以下操作,在项目生命周期内保持一套最新且经批准的要求:

()维护需求、项目计划和工作产品之间关系的所有需求变更

A、 监测

B、 管理

C、 聚集

D、 减少

信管网参考答案:B

2、The receiving  activities conduct analyses of the requirements with the requirements provider to ensure that a compatible, shared understanding  is reached on the meaning of the requirements. The result of this analysis and dialog is an (  ) set of requirements.  

A. agreed-to                        

B. agree-to          

C. agree-to-do                      

D. agree-with

信管网参考答案:A

信管网解析:这些可以接受的活动分析了需求提供者的需求,以确定对需求的含义有一个一致的、共同的理解。

信管网订阅号

信管网视频号

信管网抖音号

温馨提示:因考试政策、内容不断变化与调整,信管网网站提供的以上信息仅供参考,如有异议,请以权威部门公布的内容为准!

信管网致力于为广大信管从业人员、爱好者、大学生提供专业、高质量的课程和服务,解决其考试证书、技能提升和就业的需求。

信管网软考课程由信管网依托10年专业软考教研倾力打造,教材和资料参编作者和资深讲师坐镇,通过深研历年考试出题规律与考试大纲,深挖核心知识与高频考点,为学员考试保驾护航。面授、直播&录播,多种班型灵活学习,满足不同学员考证需求,降低课程学习难度,使学习效果事半功倍。

相关内容

发表评论  查看完整评论  

推荐文章

精选

课程

提问

评论

收藏