PMP®每日一练试题内容(2023/5/6)
试题1
项目团队分散于三个国家,项目经理必须考虑团体的协作和知识共享,以下哪项是项目经理最优先考虑的问题?查看答案
试题参考答案:D
试题2
该项目的完工估算是多少?它说明什么?()查看答案
试题参考答案:A
试题3
敏捷团队成员认为每日站会并不会增加价值,是因为小组规模太大。在回顾会上,他们提出将现有的项目团队分解成更小的小组。Scrum主管应该怎么做?查看答案
试题参考答案:D
试题4
一个关键项目可交付成果被部署在客户环境中进行用户验收测试,在执行多组测试后,由于缺陷问题,客户拒绝接受。若要避免这个问题,项目经理事先应该怎么做?查看答案
试题参考答案:A
试题解析与讨论:www.cnitpm.com/st/468718084.html
试题5
The project manager is working on a highly visible project with limited resources and strict deadline. The project is currently behind schedule. And review of the resource leveling diagram shows that some resources are allocated.查看答案
试题参考答案:D
试题6
A company CFO emails a project team member asking for in formation,about the project's progress.The communication s management plan states that the project manager should present the project status to the senior management team biweekly. What should the project manager do?查看答案
试题参考答案:C
试题7
Before approving a team member's request for an urgent leave,a project manager needs to ensure that scheduled activities will not be delayed. What should the project manager first review?查看答案
试题参考答案:D
试题8
项目经理发现由于一名资源过度承诺而导致一些任务未完成。项目经理意识到如果使用其他资源,将不会影响到关键路径。项目经理应该使用什么来满足进度计划?查看答案
试题参考答案:D
试题9
你在某大型公司担任项目经理,组织没有设立职能部门,各项目独立核算。虽然你在项目内权限很大,但与其他项目之间的沟通显得力不从心。项目经理希望有人从公司层面协调各项目之间的问题,你应该如何向公司提出建议?()查看答案
试题参考答案:C
试题10
项目组正在向相关方报告截止到当前的项目绩效情况,其中PV=110, EV=100, AC=120, 总预算为150, 成本偏差是:查看答案
试题参考答案:A
试题解析与讨论:www.cnitpm.com/st/425435334.html
信管网订阅号
信管网视频号
信管网抖音号
温馨提示:因考试政策、内容不断变化与调整,信管网网站提供的以上信息仅供参考,如有异议,请以权威部门公布的内容为准!
信管网致力于为广大信管从业人员、爱好者、大学生提供专业、高质量的课程和服务,解决其考试证书、技能提升和就业的需求。
信管网软考课程由信管网依托10年专业软考教研倾力打造,教材和资料参编作者和资深讲师坐镇,通过深研历年考试出题规律与考试大纲,深挖核心知识与高频考点,为学员考试保驾护航。面授、直播&录播,多种班型灵活学习,满足不同学员考证需求,降低课程学习难度,使学习效果事半功倍。
发表评论 查看完整评论 | |