PMP®当天每日一练试题地址:www.cnitpm.com/exam/ExamDay.aspx?t1=33
往期PMP®每日一练试题汇总:www.cnitpm.com/class/27/e33_1.html
PMP®每日一练试题(2023/4/19)在线测试:www.cnitpm.com/exam/ExamDay.aspx?t1=33&day=2023/4/19
点击查看:更多PMP®习题与指导
PMP®每日一练试题内容(2023/4/19)
试题1
While generating the status report for a budget-constrained project,the project manager identifies that the project is one week behind schedule. What should the project manager do t o bring the project back on track?查看答案
试题参考答案:A
试题解析与讨论:www.cnitpm.com/st/480389300.html
试题2
项目发起人授权项目经理编写项目章程。项目经理在收集高层次需求时,发现两位高管意见有分歧,虽然项目经理试图引导他们达成一致,但效果甚微。项目经理下—步应该怎么做?()查看答案
试题参考答案:B
试题解析与讨论:www.cnitpm.com/st/498975486.html
试题3
Spike之后找出一个低风险的方案,作为敏捷工程师,你会怎么做?查看答案
试题参考答案:C
试题解析与讨论:www.cnitpm.com/st/529559900.html
试题4
While reviewing the schedule,the project manager discovers is significant scope creep due to an unforeseen issue. What should the project manager do?查看答案
试题参考答案:C
试题解析与讨论:www.cnitpm.com/st/479987348.html
试题5
项目经理参与一个指导委员会召开的扩大会议。会议上,一位高级管理人员提出,项目团队要能保证每位成员在要求的时间完成指定的工作。这属于以下哪项管理范畴?查看答案
试题参考答案:C
试题解析与讨论:www.cnitpm.com/st/46840427.html
试题6
Local experts warn that weather condition may impact the project schedule. What should the project manager do next?查看答案
试题参考答案:A
试题解析与讨论:www.cnitpm.com/st/491123721.html
试题7
一个具体、定义明确的可交付成果正由一家公司位于某个成本较低国家的机构开发。管理层决定将该部分公司出售给另一家组织。项目经理被分配的任务是,替换该机构提供的资源,完成可交付成果。查看答案
试题参考答案:B
试题8
A project manager is leading a team developing a new online banking application.After 23 months,the team has spent U SS100,000 on development and has US$70,000 of the budgeted cost remaining. The targeted completion date is 12 months away,but the team expects completion in nine months.A team member identifies a proven off-the-shelf product t hat complies with all project specifications,can be purchased for US$60,000,and can be implemented within eight months. What should the project manager consider?查看答案
试题参考答案:D
试题解析与讨论:www.cnitpm.com/st/480991666.html
试题9
在定义范围时,项目团队识别到一个重大预算限制,并得到项目发起人的确认,若要提早识别到这个问题,项目经理应该事先做什么?查看答案
试题参考答案:D
试题解析与讨论:www.cnitpm.com/st/469386295.html
试题10
A project manager working on an IT development project dis covers that some codes supplied by a subcontractor fall to conform to project quality standards. The subcontractor refuses to change deliverables without additional payment guarantee s and extended timelines.A client debriefing is due in a few weeks. What should the project manager do?查看答案
试题参考答案:C
信管网订阅号
信管网视频号
信管网抖音号
温馨提示:因考试政策、内容不断变化与调整,信管网网站提供的以上信息仅供参考,如有异议,请以权威部门公布的内容为准!
信管网致力于为广大信管从业人员、爱好者、大学生提供专业、高质量的课程和服务,解决其考试证书、技能提升和就业的需求。
信管网软考课程由信管网依托10年专业软考教研倾力打造,教材和资料参编作者和资深讲师坐镇,通过深研历年考试出题规律与考试大纲,深挖核心知识与高频考点,为学员考试保驾护航。面授、直播&录播,多种班型灵活学习,满足不同学员考证需求,降低课程学习难度,使学习效果事半功倍。
发表评论 查看完整评论 | |