PMP®当天每日一练试题地址:www.cnitpm.com/exam/ExamDay.aspx?t1=33
往期PMP®每日一练试题汇总:www.cnitpm.com/class/27/e33_1.html
PMP®每日一练试题(2023/3/31)在线测试:www.cnitpm.com/exam/ExamDay.aspx?t1=33&day=2023/3/31
点击查看:更多PMP®习题与指导
PMP®每日一练试题内容(2023/3/31)
试题1
假设项目是按照预算单价完成 ETC工作的,则完工估算 EAC应该是:查看答案
试题参考答案:A
试题2
The installation project has a CPI of 1.03 and an SPI of 1.0. There are 14 team members and each team member had input into the final project management plan.The customer has accepted the three deliverable completed so far without complaint and the respons1bility assignment matrix has not change d since the project began. The project is being completed in a matrix environment and there are no contracts needed for t he project. Though the sponsor is happy with the status of the project, one of the team members is always complaining ab out how much time his project work is taking. Which of the following would be the BEST thing for the project manager t o do?查看答案
试题参考答案:A
试题3
对隐性知识的管理更加有难度,以下哪项应该被识别为隐性知识?()查看答案
试题参考答案:C
试题4
在规划一个敏捷项目期间,一个新的干系人参与,提出变更原始需求。为确保项目成功完成。敏捷项目经理应该做什么?查看答案
试题参考答案:C
试题5
变更控制委员会(CCB)拒绝变更请求时,项目经理应该更新什么?查看答案
试题参考答案:D
试题6
你将要接管一个被管理层认为失控的项目。但你问管理层问题出在哪里时,他们也说不出具体原因,只是告诉你进度落后、成本超支、客户不满意。那么你应该最关心以下哪项问题?查看答案
试题参考答案:B
试题解析与讨论:www.cnitpm.com/st/482543416.html
试题7
识别、评估和管理个人情绪、他人情绪以及团队情绪的能力,是:查看答案
试题参考答案:B
试题8
在一次迭代Sprint审查会议上,客户对产品印象及其深刻,要求立即发布该产品,推向市场。敏捷团队担心,因为还未解决产品维护用例问题。产品负责人将团队的担心告知客户。团队下一步应该怎么做?查看答案
试题参考答案:D
试题9
在注意到团队内部冲突后,项目经理试图强调团队中的一致意见,忽略不一致的意见来解决冲突。这是以下哪种冲突解决的技术?查看答案
试题参考答案:B
试题10
项目经理得知一名新团队成员完成了他们的第一个工作包,项目经理感到很吃惊,因为该工作包之前落后于进度计划,而现在似乎是按时完成.项目经理首先应该怎么做?查看答案
试题参考答案:A
信管网订阅号
信管网视频号
信管网抖音号
温馨提示:因考试政策、内容不断变化与调整,信管网网站提供的以上信息仅供参考,如有异议,请以权威部门公布的内容为准!
信管网致力于为广大信管从业人员、爱好者、大学生提供专业、高质量的课程和服务,解决其考试证书、技能提升和就业的需求。
信管网软考课程由信管网依托10年专业软考教研倾力打造,教材和资料参编作者和资深讲师坐镇,通过深研历年考试出题规律与考试大纲,深挖核心知识与高频考点,为学员考试保驾护航。面授、直播&录播,多种班型灵活学习,满足不同学员考证需求,降低课程学习难度,使学习效果事半功倍。
发表评论 查看完整评论 | |