PMP®每日一练试题内容(2023/2/4)

  • 试题1

    Because there are too many conflicting discussions for the project deliverables,a project for the implementation of the new system encountered a problem when it is published, leading to the project manager to leave the company. A new project manager is assigned to the pro1ect. What is the new project manager should first take action?
    由于对于项目可交付成果有太多互相矛盾的讨论,一个实施新系统的项目在发布时发生问题,导致项目经理离开公司。一名新项目经理被分配到该项目中。新项目经理首先应该采取的行动是什么?
    A、Finalize the project management plan and communicate with relevant stakeholders. 完成项目管理计划,并与相关相关方沟通。
    B、Escalate to the project sponsor and seek support to deal with the ongoing discussions. 上报项目发起人,并寻求支持,来处理正在进行的讨论。
    C、Develop a work breakdown structure and communicate with all relevant stakeholders. 制作工作分解结构,并与所有相关相关方沟通。
    D、Formalize a project charter and request approval from the sponsor and the key stakeholder. 正式确定项目章程,并要求获得项目发起人和关键相关方的批准。

    查看答案

    试题参考答案:D

    试题解析与讨论:www.cnitpm.com/st/484233276.html

  • 试题2

    在设计任务100%完成之前,项目经理正在制定交付时间长的物品的采购计划,项目经理应使用哪个紧前关系绘图法(PDM)依赖关系?
    A、开始到完成(SF)
    B、完成到完成(FF)
    C、开始到开始(SS)
    D、完成到开始(FS)

    查看答案

    试题参考答案:B

    试题解析与讨论:www.cnitpm.com/st/4622611286.html

  • 试题3

    项目章程准之后,项目经理开始使用储备分析进行预算工作,哪些文件支持这项工作?
    A、项目资金需求,成本基准和项目储备计划
    B、范围基准,风险登记册和项目进度计划
    C、质量管理计划,项目资金需求和风险登记册
    D、范围基准,时间基准和批准的变更请求

    查看答案

    试题参考答案:B

    试题解析与讨论:www.cnitpm.com/st/464776129.html

  • 试题4

    A project team is developing the work breakdown structure (WBS)for a project. Completion of the project is contingent upon delivery of multiple subprojects. To move forward wit h the WBS, what should the project team do?
    项目团队正在为项目开发工作分解结构(WBS)。该项目的完成取决于多个子项目交付。为了进行WBS,项目团队应该怎么做?
    A、Generate a decomposition of the subproject. 生成的子项目分解。
    B、Use a rolling wave planning technique until all deliverables are clear and agreed upon. 使用滚动式规划技术,直到所有交付物都清楚和一致为止。。
    C、Divide the deliverable of the subproject into work packages. 把子项目可交付成果为工作包。
    D、List missing deliverables as a risk to the risk register 将缺失的可交付成果列为风险登记册的风险。

    查看答案

    试题参考答案:B

    试题解析与讨论:www.cnitpm.com/st/4814910711.html

  • 试题5

    某项目已进行了9个月,并预计将在3个月内结束。使用挣值管理方法,挣值/计划价值的比率大于1。请问目前项目是什么状态?()
    A、超出预算
    B、落后进度
    C、低于预算
    D、提前进度

    查看答案

    试题参考答案:D

    试题解析与讨论:www.cnitpm.com/st/4893625965.html

  • 试题6

    A customer is surprised about a change made to a deliverable. The project manager explains that this change was communicated via email,and that there is a possibility that the em ail has not yet been read. What should the project manager h ave done differently?
    客户对某个可交付成果的变更感到惊讶.项目经理解释说,这一变更是通过电子邮件沟通的,客户有可能还没有阅读电子邮件.项目经理事先应该采取哪—项不同做法?
    A、Ensured that the communication cycle was complete d, and asked the customer to confirm receipt of the information 确保已完成沟通循环,并要求客户确认已收到信息
    B、Sent a follow-up email to determine if the customer re ad the first email,and obtained a read confirmation 发送一封跟进电子邮件已确定客户是否阅读了第一封电子邮件,并获得已阅读确认
    C、Called,rather than emailed,the customer with all details,and asked them to send a confirmation给客户打电话(而不是通过电子邮件)告诉客户所有详细信息,并要求他们发送确认信
    D、Developed the communications management plan 制定沟通管理计

    查看答案

    试题参考答案:D

    试题解析与讨论:www.cnitpm.com/st/478058105.html

  • 试题7

    根据项目计划,项目的状态如下∶按每小时28美元的劳动费率,工作1000小时,计划花费28000美元。监控成本时,项目经理确定成本绩效指数为0.8。项目的实际成本为40000美元。项目的进度偏差是多少?()
    A、-12000元
    B、4000美元
    C、5600美元
    D、12000美元

    查看答案

    试题参考答案:B

    试题解析与讨论:www.cnitpm.com/st/4892719590.html

  • 试题8

    一个项目可交付成果延期并错过了截止日期,团队领导为这些问题责备初级团队成员。项目经理应该怎么做?
    A、与该团队领导召开一对一的会议
    B、执行风险评估
    C、与初级团队成员协商进度计划
    D、与同事讨论,识别根本原因

    查看答案

    试题参考答案:D

    试题解析与讨论:www.cnitpm.com/st/4632821134.html

  • 试题9

    The asphalt highway project that the project manager is managing is 50% complete. The PM planned on having 4,000 square yards of asphalt placed by now,but in actuality. They've finished placing 8,000 square yards. The estimated cost forth is work was $1 per square yard. The actual cost for this work is $ 8,000.
    What does this tell the project manager?
    项目经理管理的沥青公路项目已完工50%。项目经理原本计划到现在为止铺4000平方码的沥青。而实际上他们已经铺完了8000平方码。这项工作的估算成本为1美元/平方码,实际花费8000美元。这告诉项目经理什么信息?()
    A、EV is 2. 
    B、SPI is 2. 
    C、SPI is 0.50. 
    D、SV is 0.50 

    查看答案

    试题参考答案:B

    试题解析与讨论:www.cnitpm.com/st/4896817701.html

  • 试题10

    敏捷团队完成了产品开发阶段,并核实所有测试均已通过,但客户报告对质量和性能不满意。若要避免这种情况,敏捷项目团队应该在产品发布之前做什么?
    A.召开一次回顾会议,核实项目可交付成果
    B.执行对所有需求的评审
    C.获得项目发起人的批准
    D.在计划的演示中,收集项目干系人反馈

    查看答案

    试题参考答案:D

    试题解析与讨论:www.cnitpm.com/st/5252520429.html

信管网订阅号

信管网视频号

信管网抖音号

温馨提示:因考试政策、内容不断变化与调整,信管网网站提供的以上信息仅供参考,如有异议,请以权威部门公布的内容为准!

信管网致力于为广大信管从业人员、爱好者、大学生提供专业、高质量的课程和服务,解决其考试证书、技能提升和就业的需求。

信管网软考课程由信管网依托10年专业软考教研倾力打造,教材和资料参编作者和资深讲师坐镇,通过深研历年考试出题规律与考试大纲,深挖核心知识与高频考点,为学员考试保驾护航。面授、直播&录播,多种班型灵活学习,满足不同学员考证需求,降低课程学习难度,使学习效果事半功倍。

相关内容

发表评论  查看完整评论  

报考条件查询

推荐文章

精选

课程

提问

评论

收藏