PMP®当天每日一练试题地址:www.cnitpm.com/exam/ExamDay.aspx?t1=33
往期PMP®每日一练试题汇总:www.cnitpm.com/class/27/e33_1.html
PMP®每日一练试题(2022/12/11)在线测试:www.cnitpm.com/exam/ExamDay.aspx?t1=33&day=2022/12/11
点击查看:更多PMP®习题与指导
PMP®每日一练试题内容(2022/12/11)
试题1
一些执行发起人不同意某些产品功能,因为它们阻碍了发起人的业务进行并与其矛盾。产品负责人应该怎么做?查看答案
试题参考答案:C
试题2
为一个关键业务系统开发新接口将影响500名用户项目经理希望确认项目相关方对项目的参与程度.并传递关于关键里程碑的信息,项目经理能够如何完成这项工作?查看答案
试题参考答案:A
试题3
After reviewing the monthly project performance report, the project manager when monitoring. And contingency risks. identities the need to implement a contingency plan. What does the project manager need to do?查看答案
试题参考答案:B
试题解析与讨论:www.cnitpm.com/st/491679400.html
试题4
一个组织宣布,原计划在第三季度完成的项目现在将在第二季度交付,部门经理回应说,由于第二季度有一个关键的活动,他们部门将无法支持这一可交付成果。而该部门的支持是这项可交付成果的要求,若要预防这种冲突,项目经理应该事先做什么?查看答案
试题参考答案:D
试题解析与讨论:www.cnitpm.com/st/461676864.html
试题5
项目B已启动,需要项目A正在使用的资源,而项目A的项目经理认为当前项目的资源无法按计划释放,接下来应该如何处理?查看答案
试题参考答案:C
试题6
A new project manager is assigned to a project that is already in progress. Because there are so many resources involved, the new project manager is confused about who does what. What document can the new project manager consult to clear their confusion?查看答案
试题参考答案:C
试题7
During a project with a large number of similar deliverables. a team member develops a proposal for a new quality inspect ion method.Estimating that the new method will create a time savings of approximately 15% for each deliverable,this new implementation method is not expected to affect costs or quality.What option should the project manager choose?查看答案
试题参考答案:D
试题8
一个财务项目旨在为公司客户实现风险评级计算的自动化,在工作绩效评审期间,项目发起人确定风险评级计算不准确。项目经理应该审查哪—份计划来解决这个问题?查看答案
试题参考答案:A
试题9
A project to build a 1.2 kilometer runway is budgeted at US $1 million, and is estimated to a 100 meters of runway every month. The project manager is asked by senior management to report the status to the sponsor monthly using earned value management (EVM).After six months,600 meters of the runway is completed.And US$600,000 has been spent. Which of the following should the project manager report to the sponsor?查看答案
试题参考答案:A
试题解析与讨论:www.cnitpm.com/st/489955377.html
试题10
A project is experiencing difficulties and the project status re port is due.However the project sponsor is on leave. What should the project manager do?查看答案
试题参考答案:C
试题解析与讨论:www.cnitpm.com/st/480629879.html
信管网订阅号
信管网视频号
信管网抖音号
温馨提示:因考试政策、内容不断变化与调整,信管网网站提供的以上信息仅供参考,如有异议,请以权威部门公布的内容为准!
信管网致力于为广大信管从业人员、爱好者、大学生提供专业、高质量的课程和服务,解决其考试证书、技能提升和就业的需求。
信管网软考课程由信管网依托10年专业软考教研倾力打造,教材和资料参编作者和资深讲师坐镇,通过深研历年考试出题规律与考试大纲,深挖核心知识与高频考点,为学员考试保驾护航。面授、直播&录播,多种班型灵活学习,满足不同学员考证需求,降低课程学习难度,使学习效果事半功倍。
发表评论 查看完整评论 | |