PMP®当天每日一练试题地址:www.cnitpm.com/exam/ExamDay.aspx?t1=33
往期PMP®每日一练试题汇总:www.cnitpm.com/class/27/e33_1.html
PMP®每日一练试题(2022/12/9)在线测试:www.cnitpm.com/exam/ExamDay.aspx?t1=33&day=2022/12/9
点击查看:更多PMP®习题与指导
PMP®每日一练试题内容(2022/12/9)
试题1
两个团队成员之间存在个人冲突。这两名团队成员互相不说话,项目经理预计到这将对项目执行产生直接影响。团队成员正在使用下列哪项冲突解决技巧?查看答案
试题参考答案:A
试题解析与讨论:www.cnitpm.com/st/498322940.html
试题2
During project execution.the customer requests a minor change.After performing a high-level review.the developer deter mines that the effort to make the change has minimal impact and can be absorbed What should the project manager do next?查看答案
试题参考答案:D
试题解析与讨论:www.cnitpm.com/st/477986272.html
试题3
The project has been challenging to manage. Everyone has been on edge to complete the project on time. Unfortunately,t he tension has grown to the point where team meetings have become shouting matches and little work is accomplished during the meetings. One team member asks to be excused from future team meetings, as all the shouting upsets him. Meanwhile,the sponsor has asked to attend team meetings in order to better understand how the project is going and the issues involved in completing the project, and the customer has started discussions about adding scope to the project. In this situation, it would be best for the project manager to:()查看答案
试题参考答案:C
试题4
在项目执行中途项目经理发现一种方式,可以解决并避免一个重复发生的组织问题.项目经理下—步应该怎么做?查看答案
试题参考答案:A
试题解析与讨论:www.cnitpm.com/st/464017347.html
试题5
在一个施工项目的执行阶段,由于环境问题当地居民希望停止该项目。项目经理应该怎么做?查看答案
试题参考答案:A
试题6
一次迭代工作中,一名团队成员识别到一项风险。敏捷项目经理应该执行下面那个分析?查看答案
试题参考答案:C
试题解析与讨论:www.cnitpm.com/st/530297836.html
试题7
A project is made of three activities.Activity A is lasting for 5 weeks, activity B is lasting for 6 weeks, activity C is lasting for 7 weeks, the taxis is A-B-C.While,it will take 1 week for resource distribution of activity B, and activity C will start in one week after the beginning of activity B. What is the shortest time limit for this project?查看答案
试题参考答案:C
试题8
为了确保成功交付产品,客户要求对需求进行重要更新,项目经理应该怎么做?查看答案
试题参考答案:D
试题解析与讨论:www.cnitpm.com/st/462001262.html
试题9
你作为项目经理接手了一个已经完成近50%的项目。因为这个项目报告说有很多质是问题,你打算审查经过这么长时间有什么样的趋势和偏差。下列哪一个工具对你是最有用的?查看答案
试题参考答案:B
试题10
为了使新确定的相关方尽早参与项目,scrum master建议邀请他们参加即将举行的冲刺审查会议,以向相关方证明团队正在朝着正确的方向发展,并从相关方那里获得有关团队工作完成情况的反馈。以下哪个是邀请相关方参加本次会议的另一个原因?查看答案
试题参考答案:D
信管网订阅号
信管网视频号
信管网抖音号
温馨提示:因考试政策、内容不断变化与调整,信管网网站提供的以上信息仅供参考,如有异议,请以权威部门公布的内容为准!
信管网致力于为广大信管从业人员、爱好者、大学生提供专业、高质量的课程和服务,解决其考试证书、技能提升和就业的需求。
信管网软考课程由信管网依托10年专业软考教研倾力打造,教材和资料参编作者和资深讲师坐镇,通过深研历年考试出题规律与考试大纲,深挖核心知识与高频考点,为学员考试保驾护航。面授、直播&录播,多种班型灵活学习,满足不同学员考证需求,降低课程学习难度,使学习效果事半功倍。
发表评论 查看完整评论 | |