试题1
A project manager hires A.resource to develop A.website.Th e resource abruptly quits without completing the work,and the project manager must hire another resource to complete t he job.The newly hired resource changes the website's design,which overrides the original design. How should the cost associated with the first resourced work be described?项目经理聘请一位资源开发一个网站.该资源在没有完成工作的情况下突然离职,项目经理必须聘请另一位资源来完成这项工作,新聘请的资源更改网络设计,覆盖了原有设计.应如何描述与第一位资源工作相关的成本?查看答案
试题参考答案:C
试题解析与讨论:www.cnitpm.com/st/479258179.html
试题2
在制订沟通计划时,项目经理需要考虑相关方的权力和影响,这属于以下哪项?查看答案
试题参考答案:B
试题解析与讨论:www.cnitpm.com/st/492973158.html
试题3
项目经理拥有一份在项目开始时由不同相关方提供的成功标准清单,项目经理对于如何排列这些成功标准的优先顺序感到不确定,并且明天必须在会上陈述项目章程,项目经理接下来怎么做?查看答案
试题参考答案:A
试题解析与讨论:www.cnitpm.com/st/475837722.html
试题4
After much excitement and hard work, the contract statement of work for the project is completed.Even after gaining agreement that the contract statement of work is complete, the project manager is still concerned whether it actually addresses all the buyer's needs. The project manager is about to attend the bidder conference. He asks you for advice on what to d o during the session. Which of the following is the BEST ad vice you can give him?查看答案
试题参考答案:C
试题5
A project manager confirms that at a piece of software can be given to the quality assurance group 15 days after coding begins. How is this represented on a project plan?()查看答案
试题参考答案:D
试题解析与讨论:www.cnitpm.com/st/493995757.html
试题6
项目经理进行质量评估,评估之前,比较收集数据与实际的一致性,这是在做什么?查看答案
试题参考答案:C
试题7
The project team is distributed across multiple countries. Which of the following aspects should be considered when scheduling team meetings?查看答案
试题参考答案:A
试题8
A project manager is assigned to an ongoing project. During the transition period, the project manager is provided with the budget at completion and actual cost data regarding to the project.What can be determined from this data?()查看答案
试题参考答案:D
试题9
A project manager for the seller is told by her management t hat the project should do whatever possible to be awarded incentive money. The primary objective of incentive clauses in a contract is to:查看答案
试题参考答案:C
试题10
A construction project requires the procurement of various materials. In a complex procurement process, what input should assist the project manager with proposal evaluation?查看答案
试题参考答案:B
信管网订阅号
信管网视频号
信管网抖音号
温馨提示:因考试政策、内容不断变化与调整,信管网网站提供的以上信息仅供参考,如有异议,请以权威部门公布的内容为准!
信管网致力于为广大信管从业人员、爱好者、大学生提供专业、高质量的课程和服务,解决其考试证书、技能提升和就业的需求。
信管网软考课程由信管网依托10年专业软考教研倾力打造,教材和资料参编作者和资深讲师坐镇,通过深研历年考试出题规律与考试大纲,深挖核心知识与高频考点,为学员考试保驾护航。面授、直播&录播,多种班型灵活学习,满足不同学员考证需求,降低课程学习难度,使学习效果事半功倍。
发表评论 查看完整评论 | |