PMP®每日一练试题内容(2022/8/28)
试题1
在项目上线期间,发生一个故障,项目经理下一步应该怎么做?查看答案
试题参考答案:D
试题2
Due to cross-cultural differences,stakeholders of a multinational project fail to approve the project management plan.To mitigate this issue.What should the project manager have done查看答案
试题参考答案:A
试题解析与讨论:www.cnitpm.com/st/478851342.html
试题3
评估当前风险后.项目经理意识到未考虑团队成员的暑期休假.这将影响项目,项目经理应该怎么做?查看答案
试题参考答案:B
试题4
An organization is awarded a large construction project. The project manager learns that it successfully completed a similar project and wants to use the lessons learned from that. What data analysis technique should the project manager use?查看答案
试题参考答案:A
试题5
一项活动需要一名顾问参与,在估算成本时,团队成员估算顾问费4500美元,通货膨胀余量200美元,不可预见成本缓冲300美元,项目经理接下来应该怎么做?()查看答案
试题参考答案:B
试题6
项目中的缺陷在过去三个月有所增加.项目团队必须解决这个问题.项目经理计划与项目发起人就此问题举行会议。为准备这次会议项目经理首先应该怎么做?查看答案
试题参考答案:A
试题7
项目经理确认并执行客户的变更请求,但是变更导致额外成本。根本原因分析表明,项目经理未在项目管理计划中识别负责批准变更的职权。项目经理应识别下列哪项来批准变更?查看答案
试题参考答案:D
试题解析与讨论:www.cnitpm.com/st/482708930.html
试题8
以下都是管理和分发项目信息的工具,除了:查看答案
试题参考答案:C
试题9
在一个复杂的长期项目上,项目经理采用一种方法,详细规划近期工作,并在更高层次规划未来工作。这描述的是什么?查看答案
试题参考答案:B
试题10
During a project to create an organizational business plan,the project manager facilitates strengths,weaknesses,opportunities,and threats(SWOT) analysis workshop with senior management.What progress is the project manager implementing?查看答案
试题参考答案:D
信管网订阅号
信管网视频号
信管网抖音号
温馨提示:因考试政策、内容不断变化与调整,信管网网站提供的以上信息仅供参考,如有异议,请以权威部门公布的内容为准!
信管网致力于为广大信管从业人员、爱好者、大学生提供专业、高质量的课程和服务,解决其考试证书、技能提升和就业的需求。
信管网软考课程由信管网依托10年专业软考教研倾力打造,教材和资料参编作者和资深讲师坐镇,通过深研历年考试出题规律与考试大纲,深挖核心知识与高频考点,为学员考试保驾护航。面授、直播&录播,多种班型灵活学习,满足不同学员考证需求,降低课程学习难度,使学习效果事半功倍。
发表评论 查看完整评论 | |