PMP®当天每日一练试题地址:www.cnitpm.com/exam/ExamDay.aspx?t1=33
往期PMP®每日一练试题汇总:www.cnitpm.com/class/27/e33_1.html
PMP®每日一练试题(2022/8/4)在线测试:www.cnitpm.com/exam/ExamDay.aspx?t1=33&day=2022/8/4
点击查看:更多PMP®习题与指导
PMP®每日一练试题内容(2022/8/4)
试题1
一名项目团队成员发现了在对项目进度和成本影响最小的情况下增加一个可交付成果的方法。目前项目的成本绩效指数是3,进度绩效指数是1.5。将要增加的功能不属于项目范围。你应该怎么做?查看答案
试题参考答案:A
试题2
A project manager finds that the team meetings are interrupted by individuals who arrive late and dominate discussions. To improve the effectiveness of team meetings, what should the project manager do?( )查看答案
试题参考答案:C
试题3
A project manager is initiating a new project. What is the ma in reason for identifying all stakeholders?查看答案
试题参考答案:B
试题4
When a project manager approaches the end of their company's big project, the company's organizational structure,objective and Strategies have change What should the project manager take from the following methods?()查看答案
试题参考答案:D
试题5
一个汽车,拥有5年质保,在同类产品中享有非常好的声誉,但是仅具有基本功能。请问这个汽车是属于下列哪一种情况?查看答案
试题参考答案:D
试题解析与讨论:www.cnitpm.com/st/476921844.html
试题6
为解决项目交付的性能问题,一份质量报告建议对项目测量过程进行变更。但是,如果实施变更,将影响客户的交付日期。项目经理接下来应该怎么做?查看答案
试题参考答案:D
试题解析与讨论:www.cnitpm.com/st/48258818.html
试题7
对____的全面分析将有助于识別项目的潜在风险。查看答案
试题参考答案:A
试题解析与讨论:www.cnitpm.com/st/426919630.html
试题8
Jake has been assigned the position of PM of a multi-organizational project. His organization, which is the primary performing organization, has a weak quality policy. The other organizations have no quality policy, Jake should查看答案
试题参考答案:C
试题解析与讨论:www.cnitpm.com/st/496549169.html
试题9
团队成员都在执行他们熟悉的任务,而避开他们不喜欢的任务,这造成团队成员之间的冲突。项目经理应该怎么做?查看答案
试题参考答案:A
试题10
项目经理与客户一起进行检查,确认项目可交付成果是否符合产品验收标准并满足客户的期望。这些行动属于下列哪个过程?查看答案
试题参考答案:D
试题解析与讨论:www.cnitpm.com/st/48316258.html
信管网订阅号
信管网视频号
信管网抖音号
温馨提示:因考试政策、内容不断变化与调整,信管网网站提供的以上信息仅供参考,如有异议,请以权威部门公布的内容为准!
信管网致力于为广大信管从业人员、爱好者、大学生提供专业、高质量的课程和服务,解决其考试证书、技能提升和就业的需求。
信管网软考课程由信管网依托10年专业软考教研倾力打造,教材和资料参编作者和资深讲师坐镇,通过深研历年考试出题规律与考试大纲,深挖核心知识与高频考点,为学员考试保驾护航。面授、直播&录播,多种班型灵活学习,满足不同学员考证需求,降低课程学习难度,使学习效果事半功倍。
发表评论 查看完整评论 | |