PMP®每日一练试题内容(2022/7/12)

  • 试题1

    在执行阶段外部供应商的员工在月底要罢工,在收到该消息时,项目经理应该首先更新下列哪一项?
    A、风险应对计划
    B、风险概率和评估矩
    C、风险登记簿
    D、风险管理计划

    查看答案

    试题参考答案:C

    试题解析与讨论:www.cnitpm.com/st/473834559.html

  • 试题2

    项目经理与两名持相反观点的团队成员开会。在会议中,项目经理根据两人的意见,最终采取了一个折中的方案。项目经理采用的是哪种冲突管理技术?
    A、强迫
    B、缓解
    C、撤退
    D、妥协/调解

    查看答案

    试题参考答案:D

    试题解析与讨论:www.cnitpm.com/st/498476517.html

  • 试题3

    在本季度末,项目的完工尚需绩效指数(TCPD)为1.3,项目经理必须创建成本应急计划,造成这种结果的原因是什么?
    A、项目低于预算30%
    B、项目超出预算30%
    C、项目高出完工预算(BAC)30%
    D、项目低于完工预算(BAC)30%

    查看答案

    试题参考答案:B

    试题解析与讨论:www.cnitpm.com/st/462517736.html

  • 试题4

    一个团队决定敏捷方法是否适合他们项目下一阶段的需求。不利的是,有些团队成员没有接受过适当的敏捷培训。项目经理应该如何应对敏捷培训的缺乏?
    A: 在变更请求中包含对这些团队成员的敏捷培训。
    B: 确保项目应急储备可以覆盖所有团队成员的敏捷培训
    C: 为关键团队成员创建虚拟培训课程,涵盖主要敏捷课题。
    D: 为团队成员确定并实施最具成本效益的敏捷培训
    A team decides that an agile approach fits the needs of the next phase in their project. Unfortunately, there are team members who have not had the appropriate agile training. How should the project manager respond to the lack of agile training?
    A.Include agile training for these team members in a change request.
    B.Ensure the projects contingency reserve can cover agile training for all team members.
    C.Create virtual training sessions for key team members, covering the main agile topics.
    D.Identify and implement the most cost-effective agile training for the team members.

    查看答案

    试题参考答案:D

    试题解析与讨论:www.cnitpm.com/st/525525922.html

  • 试题5

    公司正在根据现代质量管理方法来制定项目质量方针,其中哪项不需要考虑?
    A、客户满意
    B、持续改进
    C、管理层的责任
    D、监督和管理供应商

    查看答案

    试题参考答案:D

    试题解析与讨论:www.cnitpm.com/st/4966110489.html

  • 试题6

    项目经理在项目启动阶段加入一个新产品开发项目,项目经理首先应该怎么做?
    A、识别相关方
    B、获取项目资源
    C、收集产品需求
    D、制定项目管理计划

    查看答案

    试题参考答案:A

    试题解析与讨论:www.cnitpm.com/st/463447659.html

  • 试题7

    A project is seriously delayed. Earned value analysis shows t hat the project needs to be completed 10 percent faster than t he work has been going. To get the project back on track,management wants to add 10 people to an activity currently assigned to one person. The project manager disagrees,noting that such an increase will not produce an increase in speed. This is an example of:
    项目已经严重滞后。挣值分析的结果表明,项目的进度应该比当前快10%。为了让项目回到正规,管理层希望增加10个人,到原来只有一个工作的活动上来。项目经理并不同意,因为他认为这种安排不一定会导致项目进度的加快。项目经理所说的是∶
    A、The law of diminishing returns. 边际效用递减原理
    B、Fast tracking. 快速跟进
    C、Earned value. 挣值
    D、Life cycle costing. 生命周期成本

    查看答案

    试题参考答案:A

    试题解析与讨论:www.cnitpm.com/st/4686714096.html

  • 试题8

    A company was acquired by a big company that wanted to focus on its core products and services.The projects in the planning phase are being revised to include the new change management process. The project manager of a project needs continuous high-level input to ensure consistency with the new organizational structure. What should the project manager do to ensure that project changes are managed effectively?A. Reopen the requirements, expand the project to include the new change management process, and designate a team member to take full respons1bility for change management. B.Determine which change controls apply to the project, implement only those relevant and
    valuable change controls, and escalate the changes to management when necessary.
    C. Ignore the new change management process and notify the new management that the project requirements have been completed and cannot be changed.
    D. Implement new change controls and form a Change Control Board(CCB)to track and monitor changes and resolve issues and escalate issues in a timely manner.
    一家公司被一家大公司收购,这家大公司希望把重点放在其核心产品和服务上。处于规划阶段的所有项目都正在进行修定,以包含新的变更管理程序。一个项目的项目经理需要持续的高级输入,以确保与新的组织结构保持一致。若要确保项目变更得到有效管理,项目经理应该怎么做?
    A、重新开放需求,扩展项目以包含新的变更管理程序,并指定一名团队成员全权负责变更管理
    B、确定哪些变更控制适用于该项目,只实施那些相关且有价值的变更控制,并在必要时将变更升级上报给管理层
    C、忽略新的变更管理过程,并通知新的管理层,项目需求已经完成并且无法进行变更
    D、实施新的变更控制并形成变更控制委员会(CCB)以跟踪和监控变更,并及时解决问题和升级上报问题

    查看答案

    试题参考答案:D

    试题解析与讨论:www.cnitpm.com/st/4840714983.html

  • 试题9

    A conflict occurs between team member A and team member B in a project. The project manager calls both team members together and examines different solutions to the issue. Which of the following techniques does the project manager use to resolve the conflict?()
    某个项目上的团队成员A和团队成员B发成冲突,项目经理将两个团队成员叫到一起,针对问题研究了不同的解决方案,项目经理使用的是下列哪一项技巧来解决冲突泻。
    A、Confronting 面对
    B、Compromising 妥协
    C、Controlling 控制
    D、Forcing 强迫

    查看答案

    试题参考答案:A

    试题解析与讨论:www.cnitpm.com/st/4976318703.html

  • 试题10

    下列四个选项中,属于规划范围管理的输出的是∶
    A、范围管理计划、需求管理计划
    B、范围管理计划、范围说明书
    C、需求管理计划、项目文件的更新
    D、范围管理计划、组织过程资产更新

    查看答案

    试题参考答案:A

    试题解析与讨论:www.cnitpm.com/st/476414613.html

信管网订阅号

信管网视频号

信管网抖音号

温馨提示:因考试政策、内容不断变化与调整,信管网网站提供的以上信息仅供参考,如有异议,请以权威部门公布的内容为准!

信管网致力于为广大信管从业人员、爱好者、大学生提供专业、高质量的课程和服务,解决其考试证书、技能提升和就业的需求。

信管网软考课程由信管网依托10年专业软考教研倾力打造,教材和资料参编作者和资深讲师坐镇,通过深研历年考试出题规律与考试大纲,深挖核心知识与高频考点,为学员考试保驾护航。面授、直播&录播,多种班型灵活学习,满足不同学员考证需求,降低课程学习难度,使学习效果事半功倍。

相关内容

发表评论  查看完整评论  

报考条件查询

推荐文章

精选

课程

提问

评论

收藏