PMP®当天每日一练试题地址:www.cnitpm.com/exam/ExamDay.aspx?t1=33
往期PMP®每日一练试题汇总:www.cnitpm.com/class/27/e33_1.html
PMP®每日一练试题(2022/7/6)在线测试:www.cnitpm.com/exam/ExamDay.aspx?t1=33&day=2022/7/6
点击查看:更多PMP®习题与指导
PMP®每日一练试题内容(2022/7/6)
试题1
A project manager is verifying that all project-deliverable documents are updated and all issues are resolve What process does this decision查看答案
试题参考答案:B
试题解析与讨论:www.cnitpm.com/st/478719986.html
试题2
图表中的每个数据点都代表一个项目的报告期,第一个数据点最接近于0。查看答案
试题参考答案:B
试题3
项目团队包括项目经理共有15人,团队遇到意外问题,需额外增加团队资源,项目经理额外获取三名团队成员。为什么项目经理了解项目沟通渠道的数量很重要?查看答案
试题参考答案:D
试题解析与讨论:www.cnitpm.com/st/473593168.html
试题4
A project manager is assigned to a project to replace an outdated system. During installation the equipment is damaged and requires technical resources to repair it. What document must be updated to communicate this occurrence with the st keholders?查看答案
试题参考答案:A
试题解析与讨论:www.cnitpm.com/st/48362861.html
试题5
在一个施工项目中,项目经理希望外包现场边界墙的建设。潜在供应商受邀参加会议。采购公司的建筑设计师准备了一份边界墙的施工成本估算,但未与潜在供应商分享。这属于以下哪项技术?查看答案
试题参考答案:A
试题6
A customer has given you a procurement statement of work f or a complex,eight-month project that has a few unknowns.T he customer has asked you to just"get it done” and only wan ts to see you at the end of eight months when you deliver the finished project.Under these circumstance.which of the following is the BEST thing to do?查看答案
试题参考答案:A
试题解析与讨论:www.cnitpm.com/st/476191896.html
试题7
What should a project manager do when asked to complete a project's administrative closure earlier than expected查看答案
试题参考答案:D
试题8
The project team discovers that a critical activity is behind schedule. The project manager must identify when the project started to fall behind schedule. What should the project manager do next?查看答案
试题参考答案:D
试题解析与讨论:www.cnitpm.com/st/494818527.html
试题9
在执行阶段,客户告诉项目经理,三个现有工具的软件版本已更改。现在,三个接口必须以不同方式实施。项目经理应该怎么做?查看答案
试题参考答案:C
试题10
Each time you meet with your project sponsor, she emphasizes the need for cost control on your new-business project. She always asks you about cost performance in terms of which budgets have been met and which have been met and which have not. To answer her concerns,you should provide.查看答案
试题参考答案:A
试题解析与讨论:www.cnitpm.com/st/48986553.html
信管网订阅号
信管网视频号
信管网抖音号
温馨提示:因考试政策、内容不断变化与调整,信管网网站提供的以上信息仅供参考,如有异议,请以权威部门公布的内容为准!
信管网致力于为广大信管从业人员、爱好者、大学生提供专业、高质量的课程和服务,解决其考试证书、技能提升和就业的需求。
信管网软考课程由信管网依托10年专业软考教研倾力打造,教材和资料参编作者和资深讲师坐镇,通过深研历年考试出题规律与考试大纲,深挖核心知识与高频考点,为学员考试保驾护航。面授、直播&录播,多种班型灵活学习,满足不同学员考证需求,降低课程学习难度,使学习效果事半功倍。
发表评论 查看完整评论 | |