PMP®当天每日一练试题地址:www.cnitpm.com/exam/ExamDay.aspx?t1=33
往期PMP®每日一练试题汇总:www.cnitpm.com/class/27/e33_1.html
PMP®每日一练试题(2022/6/19)在线测试:www.cnitpm.com/exam/ExamDay.aspx?t1=33&day=2022/6/19
点击查看:更多PMP®习题与指导
PMP®每日一练试题内容(2022/6/19)
试题1
某公司准备实现从传统项目管理到敏捷项目管理的转型,但成员之前都从未接触过敏捷方法,敏捷教练安排组织成员进行了为期两个月的培训学习,接下来他应该怎么做?查看答案
试题参考答案:C
试题2
一家公司任命项目经理管理一个预算为2000万美元、持续时间长达36个月的高优先级项目。在项目执行过程中项目经理意识到其中一个或两个制约因素可能都不现实。项目经理首先应该怎么做?()查看答案
试题参考答案:B
试题3
在与关键项目相关方的会议上.项目经理介绍了项目的成本效益分析;一名项目相关方指出,投资回报率远低于预期。项目经理应该怎么做?查看答案
试题参考答案:B
试题4
A project manager has an agreement with a third-party supplier to deliver parts within six months. During the implementation phase,the project is cancelled. However,the supplier has already started work on this order. What should the project manager do next?查看答案
试题参考答案:A
试题解析与讨论:www.cnitpm.com/st/478425338.html
试题5
While working with the project team to prepare a network diagram, the project manager notices a series of activities can be performed in parallel, but must be finished in a specific sequence. What activity sequencing method is required?查看答案
试题参考答案:B
试题6
A project is delayed and a change is needed to obtain the desired quality level of the deliverables. The project manager issues a formal change request and communications the change to all stakeholders. The project manager then learns that this communications approach failed to meet stakeholders' expectations. What should the project manager do?查看答案
试题参考答案:A
试题解析与讨论:www.cnitpm.com/st/493725202.html
试题7
项目由于不能及时获得所需资源,已经不能继续做下去。项目经理想知道是否符合关闭项目的标准,应该查阅以下哪个文件?()查看答案
试题参考答案:C
试题解析与讨论:www.cnitpm.com/st/490632877.html
试题8
A supplier activates the project manager that,to meet the requested specifications.replacement of a specific material is required,What should the project manager to ensure that the co st baseline is unaffected?查看答案
试题参考答案:D
试题解析与讨论:www.cnitpm.com/st/478086278.html
试题9
在进行规划风险应对时,你知道一个关键任务会对项目完工产生关键影响。所以,你准备了一个弹回计划,它包括以下各种可能,除了∶查看答案
试题参考答案:D
试题10
A project manager facilitates a workshop with stakeholders t o gather product requirements and develop a requirements traceability matrix. The system developer was unable to attend the workshop, but requested a copy of the minutes to review and validate the output. The system developer then provides feedback that the listed functional requirements do not make sense when competed against the user requirements. What should the project manager do to address this?查看答案
试题参考答案:B
信管网订阅号
信管网视频号
信管网抖音号
温馨提示:因考试政策、内容不断变化与调整,信管网网站提供的以上信息仅供参考,如有异议,请以权威部门公布的内容为准!
信管网致力于为广大信管从业人员、爱好者、大学生提供专业、高质量的课程和服务,解决其考试证书、技能提升和就业的需求。
信管网软考课程由信管网依托10年专业软考教研倾力打造,教材和资料参编作者和资深讲师坐镇,通过深研历年考试出题规律与考试大纲,深挖核心知识与高频考点,为学员考试保驾护航。面授、直播&录播,多种班型灵活学习,满足不同学员考证需求,降低课程学习难度,使学习效果事半功倍。
发表评论 查看完整评论 | |