PMP高频错题(1)
[单选] 在执行阶段,市场部通知项目发起人中心小组提供了看产品的混合审查,需要进行细微变更,项目发起人指示项目经理包含变更,因为该变更不会改变范围或预算。项目经理接下来应该怎么做?
During the execution phase, marketing informs the sponsor that focus groups give the project mixed reviews and a minor change is required. The sponsor instructs the project manager to incorporate the change, because it will not change the scope or budget. What should the project manager do next?
A:记录要求的变更。
Document the requested change
B:为执行变更分配职责
Assign responsibility for implementing the change
C:与受影响方沟通该变更
Communicate the change to the affected parties
D:召集团队来评估变更的影响
Convene the team to evaluate the impact of the change.
正确答案:D 你的答案:A
解析:监控过程组 项目整合管理 实施整体变更控制的流程。
[单选] 一个项目由三个活动组成。A 活动历时 5 周,B 活动历时 6 周,C 活动历时 7 周。活动排序为 A-B-C。但是,活动 B 的资源分配要 1 周,C 在 B 活动开始 1 周后开始。则该项目最短工期是多少?
A project is made of three activities. Activity A is lasting for 5 weeks, activity B is lasting for 6 weeks, activity C is lasting for 7 weeks, the taxis is A-B-C. While, it will take 1 week for resource distribution of activity B, and activity C will start in one week after the beginning of activity B. What is the shortest time limit for this project?
A:12 周
12 weeks
B:13 周
13 weeks
C:14 周
14 weeks
D:16 周
16 weeks
正确答案:C 你的答案:B
解析:PMBOK(6) 6.5.2.2关键路径法。
[单选] 采购订单属于哪一种合同类型?
Which contract type is a purchase order?
A:工料合同
Time and material
B:成本加固定酬金合同
CPFF
C:成本补偿合同
Cost-reimbursable
D:固定总价合同
Firm fixed-price
正确答案:D 你的答案:A
解析:按照规定的价格交付规定的产品的采购订单也是固定总价合同的一种
信管网订阅号
信管网视频号
信管网抖音号
温馨提示:因考试政策、内容不断变化与调整,信管网网站提供的以上信息仅供参考,如有异议,请以权威部门公布的内容为准!
信管网致力于为广大信管从业人员、爱好者、大学生提供专业、高质量的课程和服务,解决其考试证书、技能提升和就业的需求。
信管网软考课程由信管网依托10年专业软考教研倾力打造,教材和资料参编作者和资深讲师坐镇,通过深研历年考试出题规律与考试大纲,深挖核心知识与高频考点,为学员考试保驾护航。面授、直播&录播,多种班型灵活学习,满足不同学员考证需求,降低课程学习难度,使学习效果事半功倍。
发表评论 查看完整评论 | |