在一个大型项目中,项目经理决定将风险转移给供应商是最好的风险应对措施,在项目执行期间,项目经理了解到

In a large-scale project, the project manager decides that transferring a risk to a vendor is the best risks response, during project execution, the project managers learns that the vendor is no longer financial capable of covering the risk due to internal problems, It will take three weeks for a new vendor to be appointed?

在一个大型项目中,项目经理决定将风险转移给供应商是最好的风险应对措施,在项目执行期间,项目经理了解到该供应商因内部问题不再具有财务能力来承受风险,指定新的供应商需要三周时间,在新计划生效之前,项目经理应该做些什么?A.B.D.A.Update the risk response plan to "avoid" by halting work更新风险应对计划,通过停止工作来规避

B.Meet with stakeholders to review the response plan and discuss increase the budget to accommodates the risk与相关方开会审查风险应对计划,并讨论增加预算以适应该风险

C.Proceed with project work继续进行项目工作

D.Review existing safety measures and control and assess the possibility of risk occurring审查现有的安全措施和控制措施,并评估风险发生的可能性

信管网参考答案:B

信管网解析:

B是参考答案。考点监督风险,实施风险应对措施无效,制定弹回计划。B选项比较符合题干描述的场景。参考章节11.5弹回计划的描述。

信管网订阅号

信管网视频号

信管网抖音号

温馨提示:因考试政策、内容不断变化与调整,信管网网站提供的以上信息仅供参考,如有异议,请以权威部门公布的内容为准!

信管网致力于为广大信管从业人员、爱好者、大学生提供专业、高质量的课程和服务,解决其考试证书、技能提升和就业的需求。

信管网软考课程由信管网依托10年专业软考教研倾力打造,教材和资料参编作者和资深讲师坐镇,通过深研历年考试出题规律与考试大纲,深挖核心知识与高频考点,为学员考试保驾护航。面授、直播&录播,多种班型灵活学习,满足不同学员考证需求,降低课程学习难度,使学习效果事半功倍。

相关内容

发表评论  查看完整评论  

报考条件查询

推荐文章

精选

课程

提问

评论

收藏