按照既定的变更管理程序,一项变更请求获得批准,在实施该变更过程中,一位高级管理人员对其未参与批准变更

A change request was approved according to established change management procedures, during its implementation. a senior executive expresses surprise at not being involved in this approval, since the size and cost of the change was significant. What should the project manager have done to prevent this?

按照既定的变更管理程序,一项变更请求获得批准,在实施该变更过程中,一位高级管理人员对其未参与批准变更表示很惊讶,因为该变更的规模和成本都很大。若要避免这个问题,项目经理应该事先做什么?

A.Established a change management process, the required different approval levels depending upon cost estimates制定变更管理流程,要求根据成本估算需要不同的审批级别

B.Ensured that the project team was trained to identify situations in which the senior executive should be involved in the change management process确保项目团队接受培训,以识别该高级管理人员应该参与变更管理流程的情况

C.Involve the senior executive in the design of the change management process during the project’s planning phase在项目的规划阶段,让该高级管理人员参与变更管理流程的设计

D.Consulted with the senior executive prior to submitting the change request在提交变更请求之前先咨询该高级管理人员的意见

信管网参考答案:C

信管网解析:

C是参考答案。考点在于制定项目管理计划中变更管理计划的编制,应事先考虑关键干系人在变更处理过程中的角色、职责等内容。A可以理解为是C的一项工作。

信管网订阅号

信管网视频号

信管网抖音号

温馨提示:因考试政策、内容不断变化与调整,信管网网站提供的以上信息仅供参考,如有异议,请以权威部门公布的内容为准!

信管网致力于为广大信管从业人员、爱好者、大学生提供专业、高质量的课程和服务,解决其考试证书、技能提升和就业的需求。

信管网软考课程由信管网依托10年专业软考教研倾力打造,教材和资料参编作者和资深讲师坐镇,通过深研历年考试出题规律与考试大纲,深挖核心知识与高频考点,为学员考试保驾护航。面授、直播&录播,多种班型灵活学习,满足不同学员考证需求,降低课程学习难度,使学习效果事半功倍。

相关内容

发表评论  查看完整评论  

报考条件查询

推荐文章

精选

课程

提问

评论

收藏