在新项目启动会议期间,因为项目将需要采购新设备,生产经理拒绝接受批准的章程。然后项目经理通知项目发起

During a new project’s kick-off meeting a production manager refuses to accept the approved charter because the project will require the procurement of new equipment. The project manager then informs the sponsor that the charter failed to include equipment procurement because the production manager was absent.What should the project manager do next?

在新项目启动会议期间,因为项目将需要采购新设备,生产经理拒绝接受批准的章程。然后项目经理通知项目发起人,由于生产经理缺席,章程未能包括设备釆购。项目经理下一步应该怎么做?

A.Review the production manager’s concern with the client.与客户一起审查生产经理关切的问题。

B.Record the production manager’s concern and obtain their support after the kick-off meeting.记录生产经理关切的问题,并在项目启动大会之后获得他们的支持。

C.Conduct another cost-benefit analysis that includes the production manager’s feedback.开展另一项成本效益分析,包括生产经理的反馈。

D.Explain to the production manager that equipment costs will not impact project business value.向生产经理解释设备成本不会影响项目业务价值。

信管网参考答案:C

信管网解析:

C是参考答案。当前阶段处于项目启动阶段,需要关键干系人对于项目章程理解一致。参考章节4.1.1.1B选项在启动大会后获得支持不合适,重大事项需要关键干系人确认后方可执行。

 

信管网订阅号

信管网视频号

信管网抖音号

温馨提示:因考试政策、内容不断变化与调整,信管网网站提供的以上信息仅供参考,如有异议,请以权威部门公布的内容为准!

信管网致力于为广大信管从业人员、爱好者、大学生提供专业、高质量的课程和服务,解决其考试证书、技能提升和就业的需求。

信管网软考课程由信管网依托10年专业软考教研倾力打造,教材和资料参编作者和资深讲师坐镇,通过深研历年考试出题规律与考试大纲,深挖核心知识与高频考点,为学员考试保驾护航。面授、直播&录播,多种班型灵活学习,满足不同学员考证需求,降低课程学习难度,使学习效果事半功倍。

相关内容

发表评论  查看完整评论  

报考条件查询

推荐文章

精选

课程

提问

评论

收藏