技术进步创造了一项组织需求,需要改善一个产品线的规范,从而保持领先于竞争对手。但是本财政年度的预算已

Advances in technology create an organizational need to improve a product line’s specifications to stay ahead of competitors. However, the budget for this financial year is already under significant strain, leaving very little funding available for new project.What should the project manager do?

技术进步创造了一项组织需求,需要改善一个产品线的规范,从而保持领先于竞争对手。但是本财政年度的预算已经处于巨大压力之下,新项目的可用资金很少,项目经理应该怎么做?

A.Wait for the new financial year to make any changes in product advancements等到新的财政年度再对产品改进做出任何变更

B.Perform a cost-benefit analysis of the business case to illustrate the benefits of implementing the project对商业论证执行成本效益分析,以说明实施项目的好处

C.Calculate the ROI to decide if it makes sense to proceed with the project计算ROI以确定继续执行该项目项是否有意义

D.Calculate the expected monetary value (EMV) to make the necessary recommendations to the organization计算预期货币价值(EMV)以向组织提出必要的建议

信管网参考答案:B

信管网解析:

B是参考答案。考点为商业论证阶段对项目进行可行性分析,选择合适的项目。参考PMBOK 4.1.1.1商业文件中对于成本效益分析的描述。C选项中的ROI是成本效益分析的一种做法。B选项更加合适

信管网订阅号

信管网视频号

信管网抖音号

温馨提示:因考试政策、内容不断变化与调整,信管网网站提供的以上信息仅供参考,如有异议,请以权威部门公布的内容为准!

信管网致力于为广大信管从业人员、爱好者、大学生提供专业、高质量的课程和服务,解决其考试证书、技能提升和就业的需求。

信管网软考课程由信管网依托10年专业软考教研倾力打造,教材和资料参编作者和资深讲师坐镇,通过深研历年考试出题规律与考试大纲,深挖核心知识与高频考点,为学员考试保驾护航。面授、直播&录播,多种班型灵活学习,满足不同学员考证需求,降低课程学习难度,使学习效果事半功倍。

相关内容

发表评论  查看完整评论  

报考条件查询

推荐文章

精选

课程

提问

评论

收藏