2009年上半年信息系统项目管理师考试英语真题

Many of the activities performed during the preliminary investigation are still being conducted in( ), but in much greater depth than before. During this phase, the analyst must become  fully aware of the( ) and must develop enough knowledge about the( ) and the existing systems to enable an effective solution to be proposed and implemented. Besides the( ) for process and data of current system, the deliverable from this phase also includes the( ) for the proposed system.

( )A. analysis phase                   B.  design phase  

C.  implementation phase           D. maintenance phase

( )A. main symptom                   B.  root problem

C.  final blueprint                  D.  data specification

( )A. hardware environment            B. testing environment

C. software environment             D. business environment

( )A. logical models                   B. physical models

C. design models                   D. implementation models

( )A. hardware and software specification    B. system performance specification

C. formal requirements definition        D. general problem statement

信管网解析:

初步调研阶段的许多活动在分析阶段仍然要做,但是会比以前更深入地做。在分析阶段,分析师一定要完全清楚最终蓝图并且开发出充分的关于业务环境知识和目前系统的知识以使一个有效的解决方案被提交和实施。除了当前系统的过程和数据的逻辑模型,这一阶段的产出物还包括建议系统的正式需求定义。

信管网参考答案: A,   B,   D,   A,   C