1、Developing the project schedule is often an iterative process. It determines the planned start and finish dates for project activities and milestones. Schedule development can require the review and revision of duration estimates and resource estimates to create an approved project schedule that can serve as a baseline to ( ) progress.
A. analyze
B. track
C. level
D. extend
信管网解析:
开发项目进度表通常是一个迭代过程。它确定项目活动和里程碑的计划开始和结束日期。进度计划的制定可能需要对工期估算和资源估算进行审查和修订,以创建一个批准的项目进度计划,作为()进度的基线。
A、 分析
B、 轨道
C、 水平
D、 扩展
信管网参考答案:B
2、The ( ) is a general description of the architecture of a workflow management system used by the WFMC, in which the main components and the associated interfaces are summarized. The workflow enactment service is the heart of a workflow system which consists of several .()
(1)
A. waterfall model
B. workflow reference model
C. evolutionary model
D. spiral model
(2)
A. workflow engines
B. processes
C. workflow threads
D. tasks
信管网解析:
()是WFMC使用的工作流管理系统架构的一般描述,其中总结了主要组件和相关接口。工作流执行服务是由多个工作流系统组成的工作流系统的核心
(一)
A、 瀑布模型
B、 工作流参考模型
C、 进化模型
D、 螺旋模型
(二)
A、 工作流引擎
B、 过程
C、 工作流线程
D、 任务
信管网参考答案:B、A
温馨提示:因考试政策、内容不断变化与调整,信管网网站提供的以上信息仅供参考,如有异议,请以权威部门公布的内容为准!
信管网致力于为广大信管从业人员、爱好者、大学生提供专业、高质量的课程和服务,解决其考试证书、技能提升和就业的需求。
信管网软考课程由信管网依托10年专业软考教研倾力打造,官方教材参编作者和资深讲师坐镇,通过深研历年考试出题规律与考试大纲,深挖核心知识与高频考点,为学员考试保驾护航。面授、直播&录播,多种班型灵活学习,满足不同学员考证需求,降低课程学习难度,使学习效果事半功倍。