专业信息系统项目管理师网站|培训机构|服务商(2021信息系统项目管理师学习QQ群:89253946,客服QQ:800184589)

软题库 培训课程
当前位置:信管网 >> 信息系统项目管理师 >> 试题库 >> 文章内容
信息系统项目管理师考试英语练习题(十)
来源:信管网 2020年05月13日 【所有评论 分享到微信

信息系统项目管理师考试英语练习题(十)

1、During the project, requirements change for a variety of reasons. As needs change and as work proceeds, additional requirements are derived and changes may have to be made to the existing  requirements. It is essential to manage these additions and changes efficiently and effectively. To effectively analyze the impact of the changes, it is necessary that the source of each requirement is known and the rationale for any change is documented. The project manager may,  however, want  to  track appropriate measures  of requirements volatility to judge whether new or revised ( )are necessary.  

A. proceedings                            

B. controls

C. forecasting’s                            

D. prelibations

信管网解析

参考译文:在项目过程中,由于各种原因,需求会发生变化。随着需求的变化和工作的进行,会产生额外的需求,可能需要对现有需求进行更改。必须有效地管理这些添加和更改。为了有效地分析变更的影响,有必要知道每个需求的来源,并记录任何变更的理由。然而,项目经理可能希望跟踪需求波动性的适当度量,以判断是否需要新的或修订的控制。

信管网参考答案:B

2、Project Quality Management processes include all the activities of the ( ) that determine quality policies, objectives and responsibilities so that the project will satisfy the needs for which it was undertaken.

A. project                        

B. project management team

C. performing organization        

D. customer

信管网解析:

参考译文:项目质量管理过程包括执行组织确定质量方针、目标和责任的所有活动,以使项目满足其所承担的需求。

信管网参考答案:C

扫码关注公众号

温馨提示:因考试政策、内容不断变化与调整,信管网网站提供的以上信息仅供参考,如有异议,请以权威部门公布的内容为准!

信管网致力于为广大信管从业人员、爱好者、大学生提供专业、高质量的课程和服务,解决其考试证书、技能提升和就业的需求。

信管网软考课程由信管网依托10年专业软考教研倾力打造,官方教材参编作者和资深讲师坐镇,通过深研历年考试出题规律与考试大纲,深挖核心知识与高频考点,为学员考试保驾护航。面授、直播&录播,多种班型灵活学习,满足不同学员考证需求,降低课程学习难度,使学习效果事半功倍。

相关内容

发表评论  查看完整评论  

推荐文章