试题1
远程项目团队成员请求将项目会议时间更改为在远程项目团队的工作时间内进行。然而,本地团队成员却不同意这项提议。项目经理接下来应该怎么做?查看答案
试题参考答案:A
试题2
你刚刚得知—位团队成员已经给项目增加了一项很小的额外功能。假设增加这个额外功能不会对项目进度和成本带来任何不利影响,那么针对这个变更,你应该如何做?()查看答案
试题参考答案:B
试题3
A company initiates an information technology service development pro1ect. During the risk assessment, the project team identifies that hardware group does not have sufficient resources to complete one of the deliverables on time. To complete the deliverable according to the schedule,the project manager plans to use the services of a supplier. What type of risk response strategy dose the project manager plan to use?查看答案
试题参考答案:A
试题4
When estimating a project's tasks, the project manager assumes the team is trained and experienced. The tasks require specialized skills that are not available within the current. Therefore,obtaining resources will be difficult.After the project i s completed,these skills resources will not be retained. To fill the positions on the team, which method should be utilize d?()查看答案
试题参考答案:B
试题5
一个新的会计体系正被执行,客户要求对其中一份报告进行格式变更。根据项目总工程师所言,变更足够简单,且项目经理要求立即变更。然而在发放月报时,会计人员抱怨说之前的报告中的重要信息已不再体现新的报告中。为避免这种情况,项目经理应该怎么做?查看答案
试题参考答案:B
试题6
在项目会议期间,项目相关方拒绝接受项目范围,项目经理发现该项目相关方是主要项目发起人,项目经理应该在哪个过程中认识到这名项目相关方的相关性?查看答案
试题参考答案:D
试题解析与讨论:www.cnitpm.com/st/461631309.html
试题7
项目预算为750000美元。在第42天时,项目已完成40%,成本为500000美元。在项目经理报告成本绩效指数后,客户拒绝为项目增加更多资金。若要按时按预算完成项目,项目完工尚需绩效指数必须为下列哪项?()查看答案
试题参考答案:D
试题8
在项目期间,项目经理收到需要交付新需求的通知。项目经理还了解到两名资源将从项目离开,从而影响进度。为了评价这些变更和风险对项目执行的影响,项目经理应查阅哪份文件?查看答案
试题参考答案:A
试题解析与讨论:www.cnitpm.com/st/482937847.html
试题9
A project manager completes a project in a town where the company realized a loss of 100%.The project manager's company is working on another project proposal in the same town and the management asks the project manager to come up with a rough estimate that the company can bid for the new project. The bidding must be completed within the next three days. Which of the following types of estimates should the project manager provide in this situation?查看答案
试题参考答案:A
试题10
为了适应不断变化的环境,一个信息系统建设项目建立了由复合型人才组成的查看答案
试题参考答案:C
信管网订阅号
信管网视频号
信管网抖音号
温馨提示:因考试政策、内容不断变化与调整,信管网网站提供的以上信息仅供参考,如有异议,请以权威部门公布的内容为准!
信管网致力于为广大信管从业人员、爱好者、大学生提供专业、高质量的课程和服务,解决其考试证书、技能提升和就业的需求。
信管网软考课程由信管网依托10年专业软考教研倾力打造,教材和资料参编作者和资深讲师坐镇,通过深研历年考试出题规律与考试大纲,深挖核心知识与高频考点,为学员考试保驾护航。面授、直播&录播,多种班型灵活学习,满足不同学员考证需求,降低课程学习难度,使学习效果事半功倍。
发表评论 查看完整评论 | |