  • 试题1

    Stakeholders claims that a feature is missing from a deliverable.This feature,was not mentioned in any prior discussions.and was not included in the acceptance criteria however.the stakeholders insist that the feature is necessary to take full advantage of the deliverable, What should the project manager do?
    相关方称一个可交付成果中遗漏一项功能。之前的任何讨论中都没有提到这项功能,也没有被纳入验收标准。然而,相关方却坚持认为这项功能是必要的.可以充分利用该可交付成果。项目经理应该怎么做?
    A、Defer implementing the deliverable,and submits a change request for the missing feature.
    推迟实施该可交付成果并为遗漏的功能提交变更请求。
    B、Defer implementing the deliverable and begin work on the feature. 推迟实施该可交付成果并开始遗漏功能的工作。
    C、Implement the deliverable and submit a change request for the missing feature. 实施该可交付成果并为遗漏的功能提交变更请求。
    D、Implement the deliverable and begin work on the missing feature. 实施该可交付成果并开始遗漏功能的工作。

    查看答案

    试题参考答案:A

    试题解析与讨论:www.cnitpm.com/st/4791611219.html

  • 试题2

    The sponsor asks the project manager to provide a cost estimate for a potential new project. Project funding cannot exceed US$400.000.If the rough order of magnitude (ROM) rang e is estimated between US$375,000 and US$875,000,what should the project manager advise the sponsor?
    发起人要求项目经理提供一个潜在新项目的成本估算。项目资金不能超过400000 美元。如果粗略量级估算(ROM)的区间在375000美元和875000美元之间,项目经理应告诉发起人什么?
    A、Complete the project with US$375,000,leaving a US$25,000 contingency; the project manager knows they can stay within this range by keeping tight controls  用375000美元完成项目,留下25000美元当作应急储备;项目经理知道通过严格控制,可以保持在这个成本区间之内。
    B、Provide the ROM range to the sponsor; let the sponsor decide whether to fund the next phase of the project  向发起人提供ROM区间;让发起人决定是否为项目下—阶段提供资金
    C、Assure the sponsor that a better understanding of the costs will be available upon completion of the detailed requirements  向发起人保证在完成详细需求时将会对成本有更好的认识
    D、Recommend the sponsor not proceed with the project, because it will exceed the funding Constraints  向发起人建议不要进行该项目,因为将会超出资金限制

    查看答案

    试题参考答案:B

    试题解析与讨论:www.cnitpm.com/st/4949523973.html

  • 试题3

    一个项目涉及位于全球各地的团队成员,产生了许多不同意见,新项目经理通过成功促进团队协作和问题解决提高生产力,项目经理使用的是什么工具或技术?
    A、冲突管理
    B、沟通模型
    C、群体决策技术
    D、虚拟团队

    查看答案

    试题参考答案:A

    试题解析与讨论:www.cnitpm.com/st/460926398.html

  • 试题4

    一个涉及新技术采购、多个位置、虚拟团队和外部供应商的复杂项目已成功完成。项目经理下一步应该怎么做?
    A、与项目团队庆祝
    B、召开经验教训会议
    C、更新组织知识库
    D、识别新项目的机会

    查看答案

    试题参考答案:B

    试题解析与讨论:www.cnitpm.com/st/4620117873.html

  • 试题5

    A project manager has a project that is constantly facing challenges. The sponsor is regularly unavailable to make decisions, there are massive budget overruns, team members are constantly leaving the project,and there is no practical support provided by senior management. What should the project manager do?
    项目经理管理的一个项目不断面临挑战。发起人经常无法做出决定,存在大量预算超支,团队成员不断从项目离职,高级管理层没有提供实际的支持。项目经理应该怎么做?
    A、Meet with the team to identify what is causing the problems, and escalate it to the steering committee. 与团队一起开会,以确定造成这些问题的原因,并将其升级上报给指导委员会。
    B、Meet with key stakeholders to determine if the project should be terminated. 与关键相关方开会,以确定是否应该终止项目。
    C、Replace team members who have left with new resources to complete the agreed-upon scope.
    用新资源替换离职的团队成员来完成约定的范围。
    D、Reduce the project scope to allow the remaining team members the ability to complete the project. 减少项目范围,让剩下的团队成员有能力完成项目。

    查看答案

    试题参考答案:A

    试题解析与讨论:www.cnitpm.com/st/4843621684.html

  • 试题6

    在项目施工阶段,项目发起人决定对内部设计进行重大修改。项目经理通过一对一的方式获取相关需求,这属于哪项技术?
    A、观察和交谈
    B、焦点小组会议
    C、访谈
    D、引导

    查看答案

    试题参考答案:C

    试题解析与讨论:www.cnitpm.com/st/4819122791.html

  • 试题7

    A project manager assumes a project during its execution stage and wants to review the project scope for cost settlement. The project manager discovers that some deliverables were missed in the work breakdown structure(WBS).What should the project manager do first?
    项目经理负责管理一个处于执行阶段的项目,并希望审查项目范围以进行成本结算,项目经理发现在工作分解结构(WBS)中遗漏了一项可交付成果.项目经理下一步应该怎么做?
    A、Ask the stakeholders if these missed deliverables need to be added 询问相关方是否需要添加这些遗漏的可交付成果
    B、Request that the project management office(PMO) approve additional funds for this work 请求项目管理力公室(PMO)批准这顼工作的额外资金
    C、Add the work to the WBS according to the 100 percent rule and recalculate the total project cost根据10 0%的规则将工作添加到WBS中,并重新计算项目总成本
    D、Ask subject matter experts(SMEs)to check whether these deliverables are necessary 要求主题专家(SMEs)检查这些可交付成果是否有必要

    查看答案

    试题参考答案:C

    试题解析与讨论:www.cnitpm.com/st/479275452.html

  • 试题8

    In a construction project, the project manager notices that the y can save $10 million if they use a different mounting system. What should be the project manager's reaction?
    在一个施工项目中,项目经理注意到如果他们使用不同的安装系统,将能够节约$1000万。项目经理应怎么办?
    A、Update the risk register 更新风险登记册
    B、Use the different mounting system 使用不同的安装系统
    C、Propose a change request 提出一项变更请求
    D、Exploit the opportunity 开拓该机会

    查看答案

    试题参考答案:C

    试题解析与讨论:www.cnitpm.com/st/483788917.html

  • 试题9

    成本补偿合同的例行审计中发现卖方过度报销费用。如果合同中没有定义相应的纠正措施,买方应该怎么做?
    A、执行项目费用支付
    B、在问题没有解决之前暂停支付
    C、终止合同并启动法律措施要求卖方退回过度报销的费用
    D、变更合同以要求更频繁的审计

    查看答案

    试题参考答案:A

    试题解析与讨论:www.cnitpm.com/st/4753911407.html

  • 试题10

    有效的沟通对于项目的成功至关重要。范围变更、限制条件、假设、整合与界面要求,重叠的角色和责任以及其它许多因素都对沟通提出了挑战。沟通上的障碍很可能导致∶
    A、生产力下降
    B、敌意增强
    C、士气低落
    D、冲突增加

    查看答案

    试题参考答案:D

    试题解析与讨论:www.cnitpm.com/st/475538781.html

信管网订阅号

信管网视频号

信管网抖音号

温馨提示:因考试政策、内容不断变化与调整,信管网网站提供的以上信息仅供参考,如有异议,请以权威部门公布的内容为准!

信管网致力于为广大信管从业人员、爱好者、大学生提供专业、高质量的课程和服务,解决其考试证书、技能提升和就业的需求。

信管网软考课程由信管网依托10年专业软考教研倾力打造,教材和资料参编作者和资深讲师坐镇,通过深研历年考试出题规律与考试大纲,深挖核心知识与高频考点,为学员考试保驾护航。面授、直播&录播,多种班型灵活学习,满足不同学员考证需求,降低课程学习难度,使学习效果事半功倍。

相关内容

发表评论  查看完整评论  

报考条件查询

推荐文章

精选

课程

提问

评论

收藏