PMP®每日一练试题内容(2022/6/22)

  • 试题1

    A project manager is asked to perform a cost benefit analysis for two potential projects. Project A costs US$1.2 billion, wit h potential benefits of U S$6 billion and future operating cos ts US$1.5 billion. Project B costs US$1.4 billion, with potential benefits of US$7 billion and future operating costs US$1 billion. Which project should the project manager recommend?
    项目经理被要求对两个潜在项目进行成本效益分析。项目A成本为12亿美元,潜在收益为60亿美元,未来的运营成本为15亿美元。项目B成本为14亿美元,潜在收益为70亿美元,未来的运营成本为10亿美元。项目经理应该推荐哪个项目?
    A、Project B: the potential benefits minus the costs to implement are greater than the same calculation for project A  项目B,因为潜在效益减去执行成本所得的值大于项目A所得值
    B、Project A;the cost to implement is less than project B  项目A,因为执行成本低于项目B
    C、Project B;the potential benefits minus the implementation and future operating costs are greater than the same calculation for project A  项目B,因为潜在效益减去执行成本和未来运营成本所得的值大于项目A 所得值
    D、Project A; the potential benefits plus the future operating costs are less than the same calculation for project B 项目A,因为潜在效益加上未来运营成本所得的值小于项目B所得值

    查看答案

    试题参考答案:C

    试题解析与讨论:www.cnitpm.com/st/4605315891.html

  • 试题2

    During project execution.a project manager learns that a resources role. has expanded from conducting risk analysis for this project to conducting risk analysis foe other organizational projects as well.As a result,the resource's effort and duration have increased for this project.Which impacts the schedule. What should the project manager do?
    在项目执行期间.项目经理了解到一个资源的角色已经从为该项目进行风险分析扩展到也为其他组织的项目进行风险分析。因此.该资源在该项目的工作和持续时间都有所增加,而这会影响进度。 项目经理应该做什么?
    A、Conduct an impact assessment,and process it according to the change management plan. 进行影响评估,并根据变更管理计划进行处理。
    B、Enforce the definition of that role as outlined in the project management plan. 按照项目管理计划中的说明强制执行该角色的定义。
    C、.Request more project resource to handle the additional effort.要求更多的项目资源来处理额外工作。
    D、Update the project schedule to reflect the additional effort,and inform the sponsor. 更新项目进度计划以反映额外工作,并通知发起人。

    查看答案

    试题参考答案:A

    试题解析与讨论:www.cnitpm.com/st/480822639.html

  • 试题3

    项目收尾时,项目经理审查上一个阶段收尾信息,确定所有项目工作是否完成。项目经理还必须做什么?
    A、集合团队,认可他们对项目付出的努力
    B、通知项目发起人项目已收尾
    C、在组织过程资产中更新经验教训
    D、执行偏差分析

    查看答案

    试题参考答案:C

    试题解析与讨论:www.cnitpm.com/st/462542857.html

  • 试题4

    项目发起人授权项目经理起草项目章程,但是迟迟未能提供商业论证,其他文件均已提供。项目经理应该如何行动?()
    A、暂不开始起草项目章程,等待商业论证完成
    B、帮助项目发起人编写商业论证
    C、开始起草项目章程,等商业论证提供后再修正项目章程
    D、依据提供的其他文件制定项目章程

    查看答案

    试题参考答案:A

    试题解析与讨论:www.cnitpm.com/st/4906415056.html

  • 试题5

    A project team is working on a project's new approved scope. The regulatory team was
    integral in providing input that necessitated this change. However, the team discovers that the regulatory department was not listed as a project stakeholder. What should the project manager do next?
    A. Instruct the project team to verify the need for this change.
    B. Create a new change request and ensure that the regulator y team is involved in the process.
    C. Gather further input from the regulatory team and update the existing change request to reflect the new information. 
    D. Ensure that the regulatory team is included in the change control board (CCB).
    项目团队正在研究一个项目的新批准范围,监管团队在提供对该变更必要的意见方面是不可或缺的。但是,该团队发现监管部门未被列为项目相关方。项目经理下一步应该怎么做?
    A、指示项目团队确认是否需要进行这项变更
    B、创建一项新的变更请求并确保监管团队参与这个过程
    C、收集监管团队的进一步意见,并更新现有变更请求以反映新信息
    D、确保监管团队包含在变更控制委员会(CCB)中

    查看答案

    试题参考答案:B

    试题解析与讨论:www.cnitpm.com/st/484063200.html

  • 试题6

    Advances in technology create an organizational need to imp rove a product line's specifications to stay ahead of competitors. However, the budget for this financial year is already under significant strain, leaving very little funding available for new project. What should the project manager do?
    技术进步创造了一项组织需求,需要改善一个产品线的规范,从而保持领先于竞争对手。但是本财政年度的预算已经处于巨大压力之下,新项目的可用资金很少,项目经理应该怎么做?
    A、Wait for the new financial year to make any changes i n product advancements 等到新的财政年度再对产品改进做出任何变更
    B、Perform a cost-benefit analysis of the business case to illustrate the benefits of implementing the project 对商业论证执行成本效益分析,以说明实施项目的好处
    C、Calculate the ROI to decide if it makes sense to proceed with the project 计算 ROI以确定继续执行该项目项是否有意义
    D、Calculate the expected monetary value (EMV) to make the necessary recommendations to the organization 计算预期货币价值(EMV以向组织提出必要的建议

    查看答案

    试题参考答案:B

    试题解析与讨论:www.cnitpm.com/st/4907422605.html

  • 试题7

    已经确定了总体里程牌计划和总体预算,那么项目处于哪个管理过程组?
    A、启动
    B、规划
    C、执行(
    D、监控

    查看答案

    试题参考答案:A

    试题解析与讨论:www.cnitpm.com/st/4755413746.html

  • 试题8

    在项目执行期间,项目经理与关键相关方开会提交项目状态报告。这是第四次会议,高级经理的参与度下降,他们更希望单独审查信息,而不想参加会议。项目经理接下来应该怎么做?
    A、根据请求取消项目状态报告会议和邮件报告
    B、重新评价相关方参与计划和沟通管理计划
    C、按照当前沟通管理计划执行项目
    D、咨询项目发起人,决定相关方的参与方法

    查看答案

    试题参考答案:B

    试题解析与讨论:www.cnitpm.com/st/4932111997.html

  • 试题9

    当新进公司的发起人B替代发起人A时,项目已接近完工。项目经理首先应该怎么做?
    A、更新相关方登记册
    B、与发起人B会面,确定是否需要任何项目变更
    C、根据发起人A的目标完成项目
    D、开始变更控制程序

    查看答案

    试题参考答案:A

    试题解析与讨论:www.cnitpm.com/st/495222402.html

  • 试题10

    高级管理层让项目经理针对必须优先推进的新项目实施快速评估。项目经理未完全掌握提供粗略评估所需的全部要素。项目经理首先应该怎么做?
    A、建立工作分解结构
    B、确定活动
    C、收集需求
    D、估算成本

    查看答案

    试题参考答案:C

    试题解析与讨论:www.cnitpm.com/st/4815010256.html

信管网订阅号

信管网视频号

信管网抖音号

温馨提示:因考试政策、内容不断变化与调整,信管网网站提供的以上信息仅供参考,如有异议,请以权威部门公布的内容为准!

信管网致力于为广大信管从业人员、爱好者、大学生提供专业、高质量的课程和服务,解决其考试证书、技能提升和就业的需求。

信管网软考课程由信管网依托10年专业软考教研倾力打造,教材和资料参编作者和资深讲师坐镇,通过深研历年考试出题规律与考试大纲,深挖核心知识与高频考点,为学员考试保驾护航。面授、直播&录播,多种班型灵活学习,满足不同学员考证需求,降低课程学习难度,使学习效果事半功倍。

相关内容

发表评论  查看完整评论  

报考条件查询

推荐文章

精选

课程

提问

评论

收藏