信息系统项目管理师英语复习资料:英语模拟试题与答案[3]



时间管理考题
1. During what Time Management Process are the specific activities that must be performed to produce the deliverables in the WBS identified and documented?
A. Activity Sequencing B. Activity Definition
C. Schedule Development D. Activity Duration Estimating
2. A period of time in work weeks which includes non-working days is called:
A. Elapsed Time B. Duration C. Effort D. Earned Time
3. The amount of time that an activity can be delayed from its early start without delaying the project end date is called:
A. Negative Float B. Free Float C. Total Float D. Float
E. c and d
4. What are you likely to see as a project progresses in a schedule with must fix dates and little or no slack?
A. Lots of free float B. Idle resources C. Negative float D. Positive float
5. Given the following estimates: Optimistic 3 days, Pessimistic 9 days, and most likely 6 days, what is the PERT weighted average?
A. 6 B. 4 C. 6.3 D. 6.1
6. What is the standard deviation for the estimates in the above problem?
A. 0.6 B. 2 C. 1.5 D. 0.5 E. 1
7. In crashing the schedule, you would focus on:
A. Accelerating as many tasks as possible B. Accelerating just the non-critical tasks
C. Accelerating the performance of tasks on the critical path D. None of the above
8. To calculate the late start and late finish dates for a set of tasks, you must do:
A. An analysis of the critical path B. A forwards pass
C. A backwards pass D. a and c E. all of the above
9. An activity that consumes no time or resources and shows only that a dependency exists between two activities is called:
A. A milestone B. A hammock C. A dummy activity
D. a and c E. all of the above
10. A modification of a logical relationship that allows an acceleration of the successor task is represented by:
A. Lead time B. Lag time C. Negative Lag
D. a or b E. a or c
11. Assuming a PERT weighted average computation, what is the probability of completing the project within plus-or-minus 3 standard deviations of the mean?
A. 68% B. 99.74% C. 95% D. 75%
12. Schedule variance can be determined by:
A. BCWP - ACWP B. ACWP - BCWP C. EAC - ACWP D. BCWP - BCWS
13. What is critical path?
A. The shortest path through the network, which represents the longest amount of time in which a project can be completed.
B. The path with zero float.
C. The longest path through the network, which represents the shortest amount of time in which a project can be completed.
D. The path with the most activities with the longest durations. E. b and c
14. The Time Management Process that involves identifying and documenting interactivity dependencies is called:
A. Activity Definition B. Activity Duration Estimating
C. Activity Dependencies D. Activity Sequencing
15. A network diagram that uses nodes to represent activities and arrows to show the activity dependencies and allows no loops is called:
A. AOA B. AON C. ADM D. GERT

[1]   [2]   [3]   

信管网订阅号

信管网视频号

信管网抖音号

温馨提示:因考试政策、内容不断变化与调整,信管网网站提供的以上信息仅供参考,如有异议,请以权威部门公布的内容为准!

信管网致力于为广大信管从业人员、爱好者、大学生提供专业、高质量的课程和服务,解决其考试证书、技能提升和就业的需求。

信管网软考课程由信管网依托10年专业软考教研倾力打造,教材和资料参编作者和资深讲师坐镇,通过深研历年考试出题规律与考试大纲,深挖核心知识与高频考点,为学员考试保驾护航。面授、直播&录播,多种班型灵活学习,满足不同学员考证需求,降低课程学习难度,使学习效果事半功倍。

相关内容

发表评论  查看完整评论  

推荐文章

精选

课程

提问

评论

收藏