The project manager leads an experienced team consisting of functional staff and consultants to launch a promotional version of a successful product that must be launched in time for a unique national event. What should the project manager do when developing a risk management plan?
项目经理领导一支经验丰富的团队,该团队由职能员工和顾问组成,为一项成功产品推出促销版本,为了独特的全国性活动,该产品版本必须及时推出。制定风险管理计划时,项目经理应该怎么做?
◑A.Adopt project and risks coexistence methods to deal with project risks, as this product version will be transient.采用与风险共存方法来处理项目风险,因为这种产品版本将是短暂性的。
◑B.Perform an Expected Monetary Value (EMV) analysis to determine the probability of success.执行预期货币价值(EMV)分析,确定成功概率。
◑C.Use the risk checklist from the initial product release.使用初始产品发布中的风险核对单。
◑D.Brainstorm with the team to identify risks.与团队一起头脑风暴识别风险