A project team member temporarily leaves the project and is replaced by resource with similar technical skills. Since the new resource has never participated in past project meetings, resulting in project discontinuation, what should the project manager provide to the new resources?
一位项目团队成员临时离开项目,由具有类似技术技能的资源代替,由于新资源未参加过往项目会议,导致项目中断,项目经理应向新资源提供什么?
◑A.Project Performance Report项目绩效报告
◑B.Regular training and access to project documents定期培训以及项目文件的访问权
◑C.Project management plan, including scope and schedule baseline项目管理计划,包括范围和进度基准
◑D.Work performance report工作绩效报告