A project experiences an increased number of issues. After an initial root cause analysis, the project manager suspects these issues have a common technical cause. It is believed that the risk management plan prepared by the team is not comprehensive.Which of the following tools should be used to evaluate the effectiveness of the risk management process?
A、status meeting
B、Risk reassessment
C、Technical performance management
D、Risk audits