试卷名称 2017年信息系统项目管理师最新英语模拟题(3)
考试中心《2017年信息系统项目管理师最新英语模拟题(3)》在线考试
试卷年份2017年下半年
试题题型【单选题】
试题内容

An international company is locking to expand its organization. Part of this expansion plan includes establishing a series of branch offices in selected geographical locations. The project charter has been drafted by the sponsor .who is now seeking the project manager’s help finalizing the content. Below is an excerpt of the current version of the charter.Project charter excerpt:Overall purpose; expand the company’s presence in growing marking markets and offer more local access to private customers.Objectives:-Establish a number of branch offices.-Increase the number of private customers-Offer a range of services.High level risks:-Limited knowledge of local conditions, rules and regulations-A rapidly developing unstable market-Large number of competitors looking at the same opportunities.What should be further improved in the project charter to increase the chances of a successful completion and acceptance?
A、Improve the project’s purpose to clarify the overall goal
B、Improve the risks by developing a set of clear risk response strategies
C、Improve the objectives and add definitive measure to each of them
D、Leave the charter and start converting this into a project management plan