An organization and a subcontractor have identified a potential positive impact to a project. The project manger is asked to develop a response in dealing with the positive impact. What does the project manager do?
A、Investigate options to create a risk sharing partnership with the subcontractor to manage opportunities.
B、Mitigate the risk to keep the project within scope.
C、Do nothing and comply with the project charter.
D、Transfer the opportunity to the project sponsor to develop the next steps.