软题库 移动APP 扫码下载APP 随时随地移动学习 培训课程
当前位置:信管网 >> 在线考试中心 >> 信息系统项目管理师题库 >> 试题查看
试卷名称 2017年信息系统项目管理师最新英语模拟题(1)
考试中心《2017年信息系统项目管理师最新英语模拟题(1)》在线考试
试卷年份2017年下半年
试题题型【单选题】
试题内容

A newly hired project manager is assigned three projects to close. The projects have been completed and a final review is to be performed. The project manager discovers that none of the five phase reviews were performed to have a go/no go decision.What should be done?
A、Identify all completed documents and declare the projects closed.
B、Call a meeting of stakeholders of each project to plan phase reviews that were missed
C、Confirm documents validating completion and acceptance of deliverable for each phase document lessons learned conduct a final review of it all and archive the project documents
D、Closing of these project does add any value and is a waste of time that can be applied to other projects


相关试题

推荐文章
合作网站内容