Informed of a potential project changes, the project managers performed impact analysis. The project manager then submits the change request, and offers Change Control Board (CCB) to review and approval. CCB approved changes and grant implementation. Which one of the following should the project manager update first ?
A、Risk register.
B、 Project Charter.
C、 Project Management Plan.
D、 Quality management plan.