软题库 移动APP 扫码下载APP 随时随地移动学习 培训课程
当前位置:信管网 >> 在线考试中心 >> 信息系统项目管理师题库 >> 试题查看
试卷名称 信息系统项目管理师-pmp练习题-1
考试中心《信息系统项目管理师-pmp练习题-1》在线考试
试卷年份2017年下半年
试题题型【单选题】
试题内容

You’ve been assigned to take over managing a project that should be half complete according  to the schedule. After an extensive evaluation, you discover that the project is running far behind schedule, and that the project will probably take twice the time originally estimated by the previous project manager. However, the sponsor has been told that the project is on schedule. What is the BEST course of action?
A、Try to restructure the schedule to meet the project deadline .
B、Report your assessment to the sponsor.
C、Turn the project back to the previous project manager.
D、Move forward with the schedule as planned by the previous project manager and report at the first missed milestone.


相关试题

推荐文章
合作网站内容